|
United States District Court,
E.D. Wisconsin.
RIVERFRONT LOFTS CONDOMINIUM OWNERS ASSOCIATION, Plaintiff,
v.
MILWAUKEE/RIVERFRONT PROPERTIES LIMITED PARTNERSHIP, Defendant.
.
Dec. 10, 2002.
Morton M. Grodsky, Mequon, WI, for Plaintiff.
Stephen L. Fox, Brookfield, WI, for Defendant.
DECISION AND ORDER
ADELMAN, District Judge.
In this diversity case, an association of condominium owners sued the
condominium developer for damages resulting from alleged defects in the
construction of the building. The alleged defects included: (1) a facade which
was separating from the building; (2) inadequate soundproofing; (3) insufficient
access to air conditioners; (4) unfinished work in the common area stairwells
and hallways; (5) defectively installed balconies; and (6) construction debris
left on site. Plaintiff brought tort claims, claims for breach of contract, and
claims under Wis. Stat. § 706.10(7) for breach of the implied covenant of
workmanlike performance and reasonable adequacy for purpose.
Before trial, I dismissed plaintiff's tort claims as barred by the economic loss
doctrine. The case was then tried to the court. After the trial, I rendered an
oral decision and, pursuant to Fed.R.Civ.P. 52(a), stated findings of fact and
conclusions of law. I indicated that the court had subject matter jurisdiction
based on diversity of citizenship. Plaintiff is a
citizen of Wisconsin. Defendant is an Illinois limited partnership, none of the
partners of which are residents of Wisconsin. I also determined that the
association of condominium unit owners had standing to bring the action, and
that Wisconsin substantive law governed plaintiff's claims. I rejected
plaintiff's breach of contract claims except for the claim relating to
unfinished work in the stairwells and hallways for which I found defendant
liable. However, I left open the question of damages. I rejected plaintiff's
breach of implied warranty claim concerning the balconies but reserved decision
on its other breach of implied warranty claims in order to do additional
research.
I now address plaintiff's breach of implied warranty claims relating to defects
in the facade, inadequate soundproofing, insufficient access to air
conditioners, and construction debris left on site. I also address the issue of
damages concerning defendant's failure to complete work in the stairwells and
hallways. In the course of addressing these issues, I state additional findings
of fact and conclusions of law.
I. FACTS
In 1991, defendant Milwaukee Riverfront Properties, L.P. ("MRP"), an Illinois
limited partnership, purchased an approximately 100-year-old ten-story historic
building bordering the Milwaukee River in downtown Milwaukee. Previously, the
building contained commercial and unfinished warehouse space. Acting through its
principal, David Zazove, MRP converted the building into luxury condominium
units. Among other things, MRP subdivided areas, installed walls, new plumbing,
heating and cooling systems, and hardwood floors and repaired some deterioration
in the exterior facade. The resulting units have an open, loft style with
hardwood floors, high ceilings and exposed duct-work and piping. Starting in
January 1998, MRP began selling the units but retained ownership of portions of
the common areas until January 2000, when it ceded control to plaintiff,
Riverfront Lofts Condominium Owners' Association (the "Association" or
"plaintiff"). I now turn to the relevant facts relating to each of the
construction defects alleged by plaintiff.
A. The Facade
The Riverfront Lofts building has a brick and terra cotta facade. In December
1997, approximately one month before the sale of the first condominium unit
closed, MRP hired Graef, Anhalt, Schloemer and Associates, a Milwaukee
engineering firm, to complete a condition survey of the building (the "Building
Condition Survey" or "Survey"). Bob Grothman, the author of the Building
Condition Survey, testified that he inspected the facade by standing outside at
street level and attempting to look at all four faces of the building using
binoculars. However, he stated that he could not see the south and east faces,
and could see very little of the north face.
Grothman testified that in the areas that he could see, the facade showed some
deterioration and needed tuck-pointing, but was not "tremendously bad." Based on
his observations and on the fact that he could not see most of the facade
clearly, he recommended that MRP conduct a more detailed inspection. (See also
Building Condition Survey, Trial Ex. 2 at 3-5 ("While the problem areas noted
did not appear to be significant, a detailed inspection of the facade should be
performed. This will insure that the minor deteriorated areas noted are not
indicative of a more widespread or underlying problem that could have been
missed from far away.").) Grothman also recommended that MRP repair spalls--areas
where the concrete was chipping and falling off--on the elevator machinery room
walls and on the exterior faces of the building, tuck-point brick joints, and
treat the exterior brick with a penetrating sealer. He stated that deterioration
would continue if not repaired. He testified that he had also observed that some
pieces of brick had fallen from the building.
Zazove reviewed the Building Condition Survey and had the brick joints tuck-
pointed and the spalls on the elevator machinery room walls repaired. However,
he did not order a more detailed inspection of the facade or apply a penetrating
sealer as the Building Condition Survey recommended.
Zazove testified that in 1998, MRP performed some ornamental work on the facade,
which involved replacing some masonry at the base of the building and placing
placards on the front face. Condominium unit owner, Fredrick Dichter, disputed
this testimony but acknowledged that he did not move into the building until
November 1998. I credit Zazove's testimony that MRP did ornamental facade work
in 1998.
By 2000, the terra cotta and brick in
the facade were spalling
significantly. On August 18, 2000, at the request of the Association, Dan Cohen,
an engineer, inspected the facade. He testified that he saw "large scale
degeneration" and concluded that the building had not been properly maintained.
He reported to the Association that:
Major repairs to the masonry and terra cotta are required. They are extensive
and expensive. The present state of the exterior shell is one of disintegration
and hazardous to pedestrians below....
The west and south terra cotta facing tiles are cracked,
spalled
and missing around the sills and window headers. Prior replacements used face
brick.
The brick masonry parapet wall at the northeast is cracked and separated from
the building wall with a large vertical crack.
The brick masonry back up for the terra cotta facing at the southwest corner of
the building is vertically separated from the upper story.
Water penetration into the north concrete structural frame has caused the
reinforcing steel to rust and
spall the concrete cover over the
steel.
All of the openings cut through the south wall for windows and vents are not
sealed against the weather. Brickwork is incomplete. (Trial Ex. 21 at 2.) He
stated that repair of all four faces was necessary to maintain the structural
integrity of the building and recommended that the Association solicit proposals
from contractors.
Cohen also notified the City of Milwaukee, and the City inspected the property.
The building inspector concluded that the deterioration of the terra cotta on
the west facade was so extensive that it violated a City ordinance. Thus, on
September 22, 2000, the City issued a notice of violation and ordered the
Association to "[r]epair or replace all defective or deteriorating terra cotta"
within thirty days. (Trial Ex. 3.) The City also ordered the installation of a
canopy over the sidewalk adjacent to the west face to protect pedestrians from
falling terra cotta.
Cohen testified that, in his opinion,
the deterioration was present in December 1997; although, he acknowledged having
been less certain in his deposition.
MRP
called William Dossett,
a contractor, as a witness, and
Dossett testified that he
reviewed photographs of the facade (only some of which were taken before the
Association had the facade repaired) and that, based on the photographs, he
believed that in 2000 the building was in good shape for its age and not
hazardous.
I find that the facade had deteriorated substantially by January 2000 when the
Association took over the building. Cohen is an engineer with forty years of
experience in the building industry. Thus, his opinion that substantial
deterioration was present since late 1997 is entitled to significant weight.
Grothman's testimony did not contradict Cohen's. Grothman testified that in
December 1997, he could only see the west face of the building clearly. Further,
he recommended a more thorough inspection to "insure that the minor deteriorated
areas noted [were] not indicative of a more widespread or underlying problem
that could have been missed from far away." (Trial Ex. 2 at 3-3.)
To the extent that Dossett disagreed with Cohen, I give Cohen's testimony
greater weight. Unlike Cohen, Dossett did not see the facade before it was
repaired. In addition, Dossett's testimony that the facade was in good condition
and not hazardous was not only inconsistent with Cohen's opinion but also with
that of a City building inspector.
After the City ordered plaintiff to repair the facade, plaintiff asked MRP to do
the work, but MRP declined. Plaintiff then solicited bids for the work from two
masonry contractors and hired the low bidder, Holton Bros., which repaired the
facade for $154,157. Thomas Holton, vice president of Holton Bros., testified
that approximately ten percent of the terra cotta on all four faces was close to
falling off, that substantial masonry work was needed to maintain the structural
integrity of the building, and that his company's work was necessary to
accomplish this purpose.
While agreeing that Holton Bros.'s charges were reasonable for the work that it
did, MRP disputes that the work was necessary. It points to the testimony of
Dossett, who stated that Holton Bros. could have patched some of the failing
masonry rather than replacing it altogether.
I find that Holton Bros.'s work was necessary to maintain the building's
structural integrity and that its charges were reasonable. Both Cohen and Holton
testified to this effect. Even Zazove agreed that some of the work was
necessary. The only witness who testified that Holton Bros. did more than was
necessary was Dossett, who did not actually see the facade before it was
repaired.
To pay for the $154,157 for the repair of the facade, the Association specially
assessed unit owners. MRP owned two units and paid $2,200. The Association thus
seeks $151,957 in damages.
B. Soundproofing
The Association also alleges that MRP failed to adequately soundproof the units
on the sixth through tenth floors. Condominium owner Claude Krawczyk testified
that residents can hear footsteps in the hallways outside their units and in the
units above theirs, and footsteps and running water in units on the same floor.
He stated that to muffle the impact noise from the hallways the Association
placed carpet runners in the hallways. John R. Yerges, a sound engineer, tested
the impact noise that
traveled horizontally (between units and between a unit and the hallway on the
same floor) and vertically (between units on different floors). Using a machine
that taps at a designated frequency, Yerges recorded the field impact isolation
class ("FIIC") rating of the sound. He stated that for residential condominiums
an FIIC rating of fifty-five is the accepted level for sound transmission
between units, fifty is the accepted level for sound transmission between a
common area and a unit, and that lower ratings are considered unacceptable.
Tapping in the sixth floor hallway resulted in an FIIC rating of forty-two in
the adjacent sixth floor unit, and tapping in the ninth floor hallway resulted
in an FIIC rating of thirty-nine in an adjacent ninth floor unit. The results
between units on the same floor were similar. Yerges opined that these
unacceptable FIIC ratings resulted from a failure to construct the hardwood
floors and walls so as to provide an adequate sound barrier. Specifically, he
stated that the demising walls [FN1] rest directly on top of the hardwood floors
but should have been built to rest on structural subfloors with the hardwood
abutting them.
FN1. Demising walls are the walls the divide one unit from another unit or from
a hallway.
Tapping in a unit on the seventh floor resulted in an FIIC rating of fifty-seven
in the sixth floor unit below, an acceptable rating; however, tapping in a unit
on the ninth floor resulted in an FIIC rating of forty-three in the eighth floor
unit below. Yerges opined that the low rating on the eighth floor resulted from
the construction of the floors themselves. They were built using a "sleeper"
system, which involves boards known as sleepers resting on the concrete
structural floor, and hardwood floorboards resting on top of the sleepers. He
stated that the sleeper system creates space between the hardwood floorboards
and the structural floor and allows for the easy transmission of impact noise
unless a sound dampening pad is installed.
Dossett testified that he also tested horizontal impact noise between the units.
He stated that he stood inside a unit on one of the top floors while someone
walked down the hallway. He reported that while he could hear the footsteps of a
person wearing street shoes, he could not hear someone wearing rubber soled
shoes and could not hear footsteps at all when the person walked on the carpet
runner that the Association had placed on the hallway floor.
He also testified that he had reviewed the plans and specifications for floors
five through ten, and that they called for sound insulation in the walls between
units and for rubber rings around copper water pipes, both of which he observed
in a unit that was being remodeled. The plans also provided for the demising
walls to be placed on top of the hardwood floors. He testified that,
based on his experience, this was the customary and proper way to construct the
walls. He stated that because the hardwood floors existed on floors five through
seven before the remodeling, the alternative of removing parts of the floors so
as to rest the demising walls on the structural floors would have been very
costly, ruined the existing hardwood floors and not substantially diminished
impact noise. He stated that he had never seen that type of construction in a
rehabilitated building with existing hardwood floors. Dossett testified that, on
floors eight through ten, where there were no existing hardwood floors, MRP
could have constructed the floors and walls differently or installed a
sound-dampening pad without destroying the floors. However, he said that such
construction would have been inconsistent with the construction in the rest of
the building.
Dossett also testified that constructing floors by means of a sleeper system is
the usual and best way to build a hardwood floor, because it results in a softer
floor than if the floorboards rested directly on the subfloor. Dossett admitted
that a sleeper system causes sound to be transmitted but stated that the
difference in impact noise between floors constructed with and without sleepers
is minimal.
Finally,
Dossett stated that the characteristics that define loft-style
apartments are open space, hard surfaces and little soundproofing, and that
these characteristics make sound transmission inevitable.
The Association seeks $297,041 to remove the floors, install sound dampening
material, reinstall the floors and install sound barriers in the walls.
C. Access to Air Conditioners
Plaintiff also alleges that MRP improperly installed certain air conditioners by
making them inaccessible for service and repair. Frank Karoly, president of Iron
Fireman, a heating and cooling contractor, testified that the air conditioners
in the hallways on the second and fourth floors were installed approximately
three to four inches apart. Thus, one unit could not be repaired or serviced
without removing the other. He stated that the cost of relocating the units to
make them accessible for routine service and maintenance was $12,100. He also
testified that MRP installed air conditioners in sixteen condominium units on
the fifth through tenth floors by placing them above either drywall or push-up
tile ceilings that contained no access panels. He stated that it was possible to
perform routine maintenance on such units, but that there was not enough access
to replace equipment or do major repair work. The parties stipulated that the
cost of creating such access would be $7,760.
D. Construction Debris
Plaintiff also alleges that MRP failed to clean up on-site construction dust and
debris. In 2001, the Association hired Jay Patten Enterprises to clean up
construction dust, paint and plaster, wash the stairway hand railings, steps,
doors and windows, polish and wax the stairways and clean the fire insulating
product from the trash room, doors, walls and garage floor. The total cost for
these services was $7,900.
E. Completing Work in the Stairwells and Hallways
I previously determined that MRP breached its agreement with condominium owner
Krawczyk (the "Krawczyk closing agreement"), which Krawczyk subsequently
assigned to the Association, to perform the following work:
F. Complete renovation of the south corridors on the 5th, 6th and 7th floors,
including fire escape doorways and doors, replacement of missing or damaged
flooring and repair of ceilings, beams and walls (to the same standard as
completed on floors 2, 3 and 4)....
G. Complete main and east stairwells, including floors, trim and walls and
including removal of the abandoned telephone main box located near the Riverwalk
entrance and all dead wiring going up the stairwell from the box. Clean slate
stairs....
H. Complete all corridors, including painting the 6th floor ceiling and
completing all wood trim....
(Trial Ex. 4 ¶ 6.)
The Krawczyk agreement places a dollar figure after each of the above items,
$3,000, $3,000 and $2,000 respectively. (Id.) However, the agreement also states
that if the items cost more, then MRP must pay the higher amount. (Id.
¶ 8.) Krawczyk testified that he and MRP's attorney
drafted the agreement, but that MRP's attorney insisted on placing dollar
figures next to the items. According to Krawczyk, the amounts were very rough
estimates and were not intended to bind the parties. [FN2]
FN2. Krawcyk's testimony is properly considered notwithstanding the parol
evidence rule because the contract is ambiguous with regard to the damages for
the described items. See Energy Complexes, Inc. v. Eau Claire County, 152 Wis.2d
453, 468, 449 N.W.2d 35 (1989).
The Association also obtained a bid from House Doctor, a building maintenance
contractor, to perform cleaning and repair work. The bid itself is not in
evidence. The parties stipulated that the amount of the bid was between $58,000
and $60,000; however, the record contains no evidence of precisely what work the
bid included.
Dossett testified that he recalled that in his deposition he had estimated that
the cost of repainting walls in the stairwells and refinishing the wood floors
at the landings would be around $40,000.
II. CLAIMS FOR BREACH OF IMPLIED COVENANT
The Association argues that MRP breached the covenant of workmanlike performance
and reasonable adequacy for purpose implied by Wis Stat. §
706.10(7). Section 706.10(7) states:
In the absence of an express or necessarily implied provision to the contrary, a
conveyance evidencing a transaction under which the grantor undertakes to
improve the premises so as to equip them for grantor's specified use and
occupancy, or to procure such improvement under the grantor's direction or
control, shall imply a covenant that such improvement shall be performed in a
workmanlike manner, and shall be reasonably adequate to equip the premises for
such use and occupancy.
The statute provides that a covenant will be implied into certain conveyances.
Brooks v. Hayes, 133 Wis.2d 228, 235 n. 3, 395 N.W.2d 167 (1986) ("The
legislature has apparently ... expressed the policy that a construction contract
includes an implied agreement to perform the contract in a workmanlike
manner.").
Wisconsin is not unique in recognizing an implied warranty of workmanlike
performance and/or fitness for purpose in new home sales. Forty-two states do
likewise. [FN3]
FN3. La.Rev.Stat. Ann. § 3141050; Minn.Stat. § 327A.02(1); Va.Code. Ann. §
55-701; Sims v. Lewis, 374 So.2d 298 (Ala.1979); Columbia Western Corp. v. Vela,
122 Ariz. 28, 592 P.2d 1294 (Ariz.App.1979); Wawak v. Stewart, 247 Ark. 1093,
449 S.W.2d 922
(1970); Pollard v. Saxe & Yolles Dev. Co., 12 Cal.3d 374, 115 Cal.Rptr. 648, 525
P.2d 88 (1974); Carpenter v. Donohoe, 154 Colo. 78, 388 P.2d 399 (1964); Vernali
v. Centrella, 28 Conn.Supp. 476, 266 A.2d 200 (1970); Koval v. Peoples, 431 A.2d
1284 (Del.Super.Ct.1981); Gable v. Silver, 258 So.2d 11 (Fla.Dist.Ct.App.1972),
opinion adopted by 264 So.2d 418 (Fla.1972); Bethlahmy v. Bechtel, 91 Idaho 55,
415 P.2d 698 (1966); Petersen v. Hubschman Constr. Co., 76 Ill.2d 31, 27 Ill.Dec.
746, 389 N.E.2d 1154 (1979); Barnes v. Mac Brown & Co., 264 Ind. 227, 342 N.E.2d
619 (1976); Kirk v. Ridgway, 373 N.W.2d 491 (Iowa 1985); McFeeters v. Renollet,
210 Kan. 158, 500 P.2d 47 (1972); Crawley v. Terhune, 437 S.W.2d 743 (Ky.1969);
Albrecht v. Clifford, 436 Mass. 706, 767 N.E.2d 42 (2002); Banville v. Huckins,
407 A.2d 294 (Me.1979); Loch Hill Constr. Co. v. Fricke, 284 Md. 708, 399 A.2d
883 (1979); Weeks v. Slavik Bldrs., Inc., 24 Mich.App. 621, 180 N.W.2d 503,
aff'd, 384 Mich. 257, 181 N.W.2d 271 (1970); Brown v. Elton Chalk, Inc., 358
So.2d 721 (Miss.1978); Smith v. Old Warson Dev. Co., 479 S.W.2d 795 (Mo.1972);
Chandler v. Madsen, 197 Mont. 234, 642 P.2d 1028 (1982); Norton v. Burleaud, 115
N.H. 435, 342 A.2d 629 (1975); Schipper v. Levitt & Sons, Inc., 44 N.J. 70, 207
A.2d 314 (1965); De Roche v. Dame, 75 A.D.2d 384, 430 N.Y.S.2d 390
(N.Y.App.Div.1980), appeal dismissed by 51 N.Y.2d 821, 433 N.Y.S.2d 427, 413
N.E.2d 366
(N.Y.1980); Griffin v. Wheeler-Leonard & Co., 290 N.C. 185, 225 S.E.2d 557
(1976); Velotta v. Leo Petronzio Landscaping, Inc., 69 Ohio St.2d 376, 433
N.E.2d 147, 150-51 (Ohio 1982); Jeanguneat v. Jackie Hames Constr. Co., 576 P.2d
761 (Okla.1978); Yepsen v. Burgess, 269 Or. 635, 525 P.2d 1019 (1974); Elderkin
v. Gaster, 447 Pa. 118, 288 A.2d 771 (1972); Sousa v. Albino, 120 R.I. 461, 388
A.2d 804 (1978); Rutledge v. Dodenhoff, 254 S.C. 407, 175 S.E.2d 792 (1970);
Brown v. Fowler, 279 N.W.2d 907 (S.D.1979); Dixon v. Mountain City Constr. Co.,
632 S.W.2d 538 (Tenn.1982); Humber v. Morton, 426 S.W.2d 554 (Tex.1968);
Rothberg v. Olenik, 128 Vt. 295, 262 A.2d 461 (1970); House v. Thornton, 76
Wash.2d 428, 457 P.2d 199 (1969); Gamble v. Main, 171 W.Va. 469, 300 S.E.2d 110,
113 (1983); Moxley v. Laramie Builders, Inc., 600 P.2d 733 (Wyo.1979).
Two other states have approved of the doctrine in dicta. Ass'n of Apt. Owners of
Park Towers v. Child, 1 Haw.App. 130, 615 P.2d 756 (1980); SME Indus., Inc. v.
Thompson, Ventulett, Stainback and Assocs., Inc., 28 P.3d 669, 678 n. 7 (Utah
2001).
For a brief discussion of the history and development of the doctrine, see Jeff
Sovern, Toward a Theory of Warranties in Sales of New Homes: Housing the Implied
Warranty Advocates, Law and Economics Mavens, and Consumer Psychologists Under
One Roof, 1993 Wis. L.Rev. 13, 19-23.
However, few reported Wisconsin cases discuss the implied covenant. Other than
Brooks only three appellate decisions do so, all unpublished. In Bero v. White
House Homes, Inc., No. 78-618, 1979 WL 30471, **2-3, 1979 Wisc.App. LEXIS 3267,
at *4-6 (May 31, 1979), the court of appeals concluded that Wis. Stat. §
706.10(7) implied a warranty in a contract for the construction and sale of a
home and that, based on the warranty, the buyer could recover for latent
defects. In Maltbey v. Nu Way Bldrs., Inc., No. 84-921, 1985 WL 188050, *1, 1985
Wisc.App. LEXIS 3225, at *1 (Mar. 26, 1985), the court of appeals rejected the
plaintiff's claim to an implied warranty of habitability in new home sales by a
builder-vendor. The court cited § 706.10(7), but determined without explanation
that it did not apply. Id., 1985 WL 188050, *1, 1985 Wisc.App. LEXIS 3225, *3.
More recently, in Shisler v. Frank, No. 97-2310, 1998 WL 255206, **5-6, 1998
Wisc.App. LEXIS 1546, at * 13-14 (Ct.App. May 21, 1998), the court of appeals
held "that there is an implied warranty of fitness for the intended use in the
contract for sale of a home or condominium from the builder-vendor to the
builder-vendee." The court based its ruling on related state supreme court
decisions and cases from other jurisdictions, but did not cite § 706.10(7). Id.,
1998 WL 255206, **2-5, 1998 Wisc.App. LEXIS 1546, **6-11.
I now turn to plaintiff's breach of implied covenant claims and will
decide them as I believe the state supreme court would, if required to do so.
Allstate Ins. Co. v. Menards, Inc., 285 F.3d 630, 636-37 (7th Cir.2002).
A. Reason for Implied Covenant
Traditionally, sales of real estate including new homes were governed by the
rule of caveat emptor. However, modern courts have rejected the rule. Richard A.
Lord, Williston on Contracts § 50:30 (4th ed.2000) (stating that the modern
trend rejects the rule of caveat emptor in new home sales); see Ollerman v.
O'Rourke Co., 94 Wis.2d 17, 38, 288 N.W.2d 95 (1980) ("This court has moved away
from the rule of caveat emptor in real estate transactions, as have courts in
other states."); Shisler, 1998 WL 255206, *3, 1998 Wisc.App. LEXIS 1546, at *8
(discussing the Wisconsin Supreme Court's gradual rejection of the rule).
Recognizing the changed context of most real estate transactions, courts and
legislatures have replaced the rule with implied warranties. As the Illinois
Supreme Court explained,
Many new houses are, in a sense, now mass produced.... The nature of the
construction methods is such that a
vendee has little or no opportunity to inspect. The vendee is making a major
investment, in many instances the largest single investment of his life. He is
usually not knowledgeable in construction practices and, to a substantial
degree, must rely upon the integrity and the skill of the builder-vendor, who is
in the business of building and selling houses. The vendee has a right to expect
to receive that
for which he has bargained and that which the builder-vendor has agreed to
construct and convey to him, that is, a house that is reasonably fit for use as
a residence.
Petersen v. Hubschman Constr. Co., Inc., 76 Ill.2d 31, 27 Ill.Dec. 746, 389
N.E.2d 1154, 1157 (1979); accord Shisler, 1998 WL 255206, **4-5, Wisc.App. LEXIS
1546, at * 12-13 (quoting same passage with approval).
Thus, implied warranties in new home sales were created because (1) the
builder-vendor is generally in a better position than the buyer to know if
serious defects are present; (2) the buyer relies on the builder-vendor's
expertise and reasonably expects that the builder-vendor will complete the
structure in a workmanlike manner; and (3) the buyer reasonably expects to
obtain an adequate structure and thus, any defects undermining a structure's
adequacy undermine the essence of the parties' bargain. Id.; accord Albrecht,
767 N.E.2d at 46; Degnan v. Executive Homes, Inc., 215 Mont. 162, 696 P.2d 431,
433 (1985); Atherton Condo. Apt.-Owners Ass'n Bd. of Dirs. v. Blume Dev. Co.,
115 Wash.2d 506, 799 P.2d 250, 259 (1990).
B. Whether Statutory Preconditions for Implying Covenant Are Met
To determine whether the Association may avail itself of the implied
covenant, I begin with the language of the statute. Under the statute, a
covenant is implied when there is: (1) a conveyance from the grantor to the
grantee, (2) "evidencing a transaction under which the grantor undertakes to
improve the premises" or "to procure such improvement under grantor's
direction", (3) for the grantee's "specified use and occupancy." Wis Stat. §
706.10(7).
Plaintiff has established these elements. First, in sales occurring between
January 1998 and September 2000, MRP conveyed to unit owners residential units
and, in January 2000, transferred control over the common areas to the
Association. Thus, there was a conveyance.
Second, the Association has proven that MRP "agree[d] to improve the premises."
An "improvement" is "[a] valuable addition made to property (usually real
estate) or an amelioration in its condition, amounting to more than mere repairs
or replacement, costing labor or capital, and intended to enhance its value,
beauty or utility or to adapt it for new or further purposes." Black's Law
Dictionary 757 (6th ed.1990). The substantial renovations performed by MRP to
the Riverfront Lofts building transformed commercial and warehouse space into
luxury residential lofts. MRP fixed exterior masonry, subdivided areas, added
walls, floors, heating and cooling systems and plumbing. Thus, MRP improved the
property. [FN4]
FN4. Courts in other jurisdictions have also found that implied warranties apply
to the substantial renovation of existing structures and not simply new
construction. E.g., Towers Tenant Ass'n, Inc. v.
Towers Ltd. P'ship, 563 F.Supp. 566, 575 (D.D.C.1983); Council of Unit Owners of
Breakwater House Condo. v. Simpler, 603 A.2d 792, 795 (Del.1992); VonHoldt v.
Barba & Barba Constr., Inc., 175 Ill.2d 426, 222 Ill.Dec. 302, 677 N.E.2d 836,
839 (1997); Licciardi v. Pascarella, 194 N.J.Super. 381, 476 A.2d 1273, 1274
(1983).
MRP argues that "improvement" under the statute is limited to those specific
elements of the building that it actually worked on, that it did not work on the
facade and, therefore, the implied covenant does not apply to the facade.
However, MRP's undertaking with respect to the building was very broad and
consisted of literally transforming the entire property so that it could be used
for residences. Further, MRP did perform some work on the facade. Where the
scope of a builder's improvement of property is as extensive as it was here, it
would be unreasonable to interpret the statute as implying a covenant only with
respect to those parts of the building on which the builder performed work. To
read the implied warranty so narrowly would undermine the purpose of the
statute, which is to encourage the construction of reasonably adequate
structures. A builder renovating an existing structure could avoid liability by
simply failing to correct existing defects even if the result was an inadequate
structure.
Finally, the Association has shown that MRP improved the premises for its
members' "specified use and occupancy." See Wis. Stat. § 706.10(7). The purpose
of the improvements was to permit the building to be used for residences. Such
anticipated use is sufficiently specified to trigger the implied covenant.
This conclusion is buttressed by Wisconsin cases allowing purchasers of property
intended to be used as a residence to recover from builder-vendors for negligent
construction. See Oremus v. Wynhoff, 20 Wis.2d 635, 123 N.W.2d 441 (1963);
Fisher v. Simon, 15 Wis.2d 207, 112 N.W.2d 705 (1961). In Fisher, the plaintiffs
sued for construction defects in a new house that they had purchased as a
residence. Similarly, in Oremus, the plaintiffs sued for construction defects in
an apartment building.
C. Whether Defendant Breached Covenant
1. Scope of Covenant and Criteria for Determining Breach
Because plaintiff has shown that MRP's conveyances of condominiums to unit
owners are within § 706.10(7), the statute implies a covenant that "improvement[s]
... be performed in a workmanlike manner and ... be reasonably adequate to equip
the premises for [the grantee's] use and occupancy." Thus, the covenant includes
two warranties, a warranty of workmanlike performance and a warranty that the
building will be reasonably adequate for use and occupancy.
Like the Wisconsin statute, courts in other jurisdictions and commentators
distinguish between implied warranties covering the manner of
performance and those relating to the adequacy of the resulting product. E.g.,
Bednarski v. Hideout Homes & Realty, Inc., 711 F.Supp. 823, 827 (M.D.Pa.1989);
Council of Unit Owners of Breakwater House Condo., 603 A.2d at 795; Schmeck v.
Sea Oats Condo. Ass'n Inc., 441 So.2d 1092, 1097 (Fla.App.1983); Wimmer v. Down
E. Props., Inc., 406 A.2d 88, 93 (Me.1979); Albrecht, 767 N.E.2d at 46 n. 7;
George B. Gilmore Co. v. Garrett, 582 So.2d 387, 391 (Miss.1991); Chandler v.
Madsen, 197 Mont. 234, 642 P.2d 1028, 1031-32 (1982); Aronsohn v. Mandara, 98
N.J. 92, 484 A.2d 675, 682-83 (1984); Kennedy v. Columbia Lumber & Mfg. Co.,
Inc., 299 S.C. 335, 384 S.E.2d 730, 736 (1989); Meadowbrook Condo. Ass'n v. S.
Burlington Realty Corp., 152 Vt. 16, 565 A.2d 238, 240-41 (1989); Timothy Davis,
The Illusive Warranty of Workmanlike Performance: Constructing a Conceptual
Framework, 72 Neb. L.Rev. 981, 1017-20 (1992). [FN5] I will discuss each type of
implied
warranty to determine the standard that a builder- vendor must meet to satisfy
it.
FN5. The Texas Supreme Court recently described the relationship between the two
types of warranties:
These two implied warranties parallel one another, and they may overlap. For
example, a builder's inferior workmanship could compromise the structure and
cause the home to be unsafe [thereby breaching the implied
warranty habitability]. But a builder's failure to perform good workmanship is
actionable even when the outcome does not impair habitability. Similarly, a home
could be well constructed and yet unfit for human habitation if, for example, a
builder constructed a home with good workmanship but on a toxic waste site.
Centex Homes v. Buecher, No. 00-0479, 2001 WL 1946128, at *6 (Tex. Aug.29, 2002)
(internal citation omitted).
a. Workmanlike Performance
"Workmanlike" means "worthy of a good workman," "well performed" or
"skillful." Webster's Third New International Dictionary 2635 (3d ed.1986). If
faced with the question, I believe that the Wisconsin Supreme Court would
conclude that the standard for determining whether a builder-vender's
performance is "workmanlike" is the same as the standard of care for common law
negligence. See Hal G. Block, As the Walls Came Tumbling Down: Architects'
Expanded Liability Under Design-Build/Construction Contracting, 17 J. Marshall L.Rev. 1, 18 n. 86 (1984) (stating that warranty of workmanlike performance is a
warranty not to act negligently); Michael M. Greenfield, Consumer Protection in
Service Transactions--Implied Warranties and Strict Liability in Tort, 1974 Utah
L.Rev. 661, 666 (stating that implied warranty of workmanlike performance
requires non-negligent performance).
Borrowing from tort law is consistent with the Wisconsin Supreme Court's view
that poor workmanship under a contract gives rise to claims for both breach of
contract and negligence. [FN6] See Oremus, 20 Wis.2d at 643, 123 N.W.2d 441;
Fisher, 15 Wis.2d at 211, 112 N.W.2d 705. The standard of non- negligence
requires a builder to perform construction or remodeling work "with the same
degree of care and skill and ... provide such suitable materials as are used and
provided by contractors of reasonable prudence, skill, and judgment in similar
construction." Wis. Jury Instructions--Civil 1022.4 (1992). The standard is the
same whether a plaintiff labels the claim as one in tort or contract. For
example, in Fisher, which involved a tort claim, the court stated that
"accompanying every contract is a common law duty to perform it with care and
skill, and a failure to do so is a tort as well as a breach of contract." 15
Wis.2d at 211, 112 N.W.2d 705. Thus, the court's conclusion that a
builder/vendor has a duty "to use ordinary care in the construction of the
[house] or the same degree of care used by similar building contractors in this
vicinity in constructing houses," id. (internal quotation marks and citation
omitted), applies equally whether the claim sounds in tort or contract.
FN6. Recent Wisconsin Supreme Court decisions adopting and applying the economic
loss doctrine call into doubt whether the court would today
hold that a party has a negligence claim under such circumstances. See, e.g.,
Wausau Tile, Inc. v. County Concrete Corp., 226 Wis.2d 235, 593 N.W.2d 445
(1999); State Farm Mut. Auto. Ins. Co. v. Ford Motor Co., 225 Wis.2d 305, 592
N.W.2d 201 (1999); Daanen & Janssen, Inc. v. Cedarapids, Inc., 216 Wis.2d 395,
573 N.W.2d 842 (1998); see also Mose v. Tedco Equities, 228 Wis.2d 848, 858-59,
598 N.W.2d 594 (Ct.App.1999) (extending the doctrine to real estate
transactions). Indeed, I previously dismissed the Association's tort claims as
barred by the economic loss doctrine. However, the decisions have no bearing on
the standard of care that a builder-vendor must meet in order to satisfy implied
contractual warranties.
Likewise, in Brooks, a contract case, the supreme court held that "although the
construction contract [at issue] was silent with
regard to the level of performance or standard of care required of [the
developer], the contract implicitly impose[d] on [the developer] the duty to
perform with due care." 133 Wis.2d at 234, 395 N.W.2d 167. The court explained
that " 'accompanying every contract is a common-law duty to perform with care,
skill, reasonable expediency and faithfulness the thing they agreed to be done,
and a negligent failure to observe any of these conditions is a tort, as well as
a breach of contract.' " Id. at 235, 395 N.W.2d 167 (quoting Colton
v. Foulkes, 259 Wis. 142, 146, 47 N.W.2d 901 (1951)). Thus, in determining the
standard of care for construction under a contract, the Wisconsin Supreme Court
has treated tort and contract claims as interchangeable.
Further, the majority of jurisdictions that recognize an implied warranty of
workmanlike performance in contracts between a builder/seller and a new
homeowner employ a negligence standard to determine whether the performance was
workmanlike. Moreover, like Wisconsin, they look to local industry practices to
determine negligence. For example, in assessing whether a builder's performance
satisfies the implied warranty of workmanlike performance, Texas courts ask
whether the builder "construct[ed] the home in the same manner as would a
generally proficient builder engaged in similar work and performing under
similar circumstances." Centex Homes, 2001 WL 1946128, at *5; accord Wimmer, 406
A.2d at 93 ("The test is one of reasonableness, not perfection, the standard
being, ordinarily, the quality of work that would be done by a worker of average
skill and intelligence."); Becker v. Graber Builders., Inc., 149 N.C.App. 787,
561 S.E.2d 905, 909 (2002) (applying "the standard of workmanlike quality then
prevailing at the time and place of construction").
b. Reasonably Adequate for Intended Use and Occupancy
As discussed, the second warranty implied by § 706.10(7), that the premises
are reasonably adequate for their intended use and occupancy, relates
to the quality of the resulting property, not the builder's manner of
performance. Thus, a showing of negligence by the builder or developer is not
required. See Centex Homes, 2001 WL 1946128, at *6 (quoting Davis, supra, at
1015); see also Crowder v. Vandendeale, 564 S.W.2d 879, 882 (Mo.1978), overruled
on other grounds by Sharp Bros. Contracting Co. v. Am. Hoist & Derrick Co., 703
S.W.2d 901 (Mo.1986).
The citation to Earl Millikin, Inc. v. Allen, 21 Wis.2d 497, 124 N.W.2d 651
(1963) in the legislative comment following § 706.10(7) suggests that the
drafters intended that this be the rule in Wisconsin. In Earl Milliken, the
court addressed a commercial tenant's obligation to pay rent to a
builder/landlord for property to be used as a retail store even though the
property had no water supply. The court said that the "[c]ovenant of possession
[in the lease and construction agreement] implies not only that the tenant will
be able to physically occupy the premises ... but that he will also be able to
use the premises for its intended purpose." Id. at 501, 124 N.W.2d 651. The
building's intended purpose, use as a retail store, required a water supply for
which the grantee had expressly contracted; thus, the landlord violated the
covenant. Id. at 501-02, 124 N.W.2d 651. No showing of negligence was required.
The state court of appeals reached the same result in Shisler, where it found
the builder liable for breach of an implied warranty of fitness based on
flooding in the basements of the plaintiffs' new condominium units even though
the trial court had
expressly declined to find that the builder had acted negligently. 1998 WL
255206, **5-6, 1998 Wisc.App. LEXIS 1546, at *14-15. The court of appeals
focused only on the resulting condominium units and whether they were fit for
occupancy, not the builder's manner of performance. Id. And, although Shisler is
an unpublished decision, its analysis of Wisconsin law is thorough and its
reasoning persuasive.
However, not every defect will violate this implied warranty. Rather, the
defect must make the property not "reasonably adequate" for its intended "use
and occupancy" and, thus, be so substantial that it undermines the essence of
the parties' bargain. Wisconsin courts have interpreted an analogous warranty,
the implied warranty of habitability in residential leases, to be violated only
when defects were so substantial that they made the premises uninhabitable. In
Pines v. Perssion, 14 Wis.2d 590, 111 N.W.2d 409 (1961), the state supreme court
found that the landlord breached the implied warranty because the apartment was
"not in a condition reasonably and decently fit for occupation" due to its
"inadequate electrical wiring, kitchen sink and toilet in disrepair, furnace in
disrepair, handrail on stairs in disrepair, screens on windows and doors
lacking." Id. at 593-96, 111 N.W.2d 409. Similarly, in Denham v. Madole, 194
Wis. 583, 585, 217 N.W. 423 (1928), the court permitted a commercial tenant to
abandon his basement billiard hall rental unit
when leaking water and excessive moisture began causing damage to goods and the
occupants' health.
Courts in other jurisdictions have also held that only substantial defects
violate the implied warranty of fitness for new homes. E.g., Gaito v. Auman, 313
N.C. 243, 327 S.E.2d 870, 874 (1985) (stating that dwelling must be
"sufficiently free from major structural defects"); Centex Homes, 2001 WL
1946128, at *6 (stating that the warranty is breached by conditions that are
"dangerous, hazardous, or detrimental to ... life or safety"); Stuart v.
Coldwell Banker Commercial Group, Inc., 109 Wash.2d 406, 745 P.2d 1284, 1289- 90
(1987) (stating that warranty is breached by "structural and egregious"
defects). Relatively minor defects--those that do not implicate the property's
habitability or structural integrity--do not violate the implied warranty. E.g.,
Aronsohn v. Mandara, 98 N.J. 92, 484 A.2d 675, 681-82 (1984) (holding that
defective patios did not breach the implied warranty of habitability); Stuart,
745 P.2d at 1289-90 (stating that walkways and decks which failed to meet water
tightness requirements might not be sufficient to breach the implied warranty).
Whether a defect is substantial or not is not a precise determination. See Jean
C. Love, Landlord's Liability for Defective Premises: Caveat Lessee, Negligence,
or Strict Liability, 1975 Wis. L.Rev. 19, 101-02. Thus, in the context of
residential rental units, the Wisconsin Supreme Court has considered
whether the apartment complies with fundamental aspects of local housing codes.
The Pines court relied heavily on the landlord's violation of local housing
codes in concluding that the implied warranty of habitability had been breached.
The court said,
Legislative and administrative rules, such as the safe place statute, building
codes and health regulations, all impose certain duties on a property owner with
respect to the condition of the premises. Thus, the legislature has made a
policy judgment--that it is socially (and politically) desirable to impose these
duties on a property owner--which has rendered the old common law rule [of
caveat emptor] obsolete. Pines, 14 Wis.2d at 595-96, 111 N.W.2d 409. The court
concluded that the landlord
breached the implied warranty because the apartment did not comply with the
housing code in several key respects--there was "inadequate electrical wiring,
kitchen sink and toilet in disrepair, furnace in disrepair, handrail on stairs
in disrepair, screens on windows and doors lacking." Id. at 596, 111 N.W.2d 409.
Similarly, in Diamond Homes, Inc. v. Bodovinac, 42 Wis.2d 683, 691-92, 168
N.W.2d 75 (1969), the court relied on the builder's non-compliance with city
grading requirements to hold it liable to the home- buyers for breach of
contract.
Courts in other jurisdictions also treat local housing and building codes as a
benchmark in determining whether a new home satisfies the implied warranty of
fitness or habitability. E.g., Carpenter v. Donohoe, 154 Colo. 78, 388 P.2d 399,
402 (1964); Vantage View, Inc. v. Bali E. Dev. Corp., 421 So.2d 728, 730
(Fla.Dist.Ct.App.1982), overruled on other grounds by Dania Jai- Alai Palace,
Inc. v. Sykes, 450 So.2d 1114 (Fla.1984); Schiro v. W.E. Gould & Co., 18 Ill.2d
538, 165 N.E.2d 286, 290-91 (1960); Albrecht, 767 N.E.2d at 47; Atherton Condo.
Apt.-Owners Ass'n Bd. of Dirs., 799 P.2d at 258-60. Once again, however, not
every deviation from a building code constitutes a breach. The violation must be
fundamental to the habitability of the building. Compare Schiro, 165 N.E.2d at
290-91 (holding that violation of plumbing and sewage disposal routing
requirements breached implied warranty) and Atherton Condo. Apt.-Owners Ass'n,
799 P.2d at 258-60 (holding that violation of fire code provision relating to
construction of floors and ceilings could breach implied warranty) with Stuart,
745 P.2d at 1289-90 (holding that violation of water tightness requirements for
walkways and decks might not be sufficient to breach warranty).
2. Application of Criteria to Plaintiff's Claims
a. Facade
I conclude that with respect to the facade, a preponderance of the evidence
shows that MRP breached the implied covenant of reasonable adequacy by conveying
a structurally compromised building with a facade that was noncompliant with the
local building code. As discussed, the evidence
discloses that the facade had substantially deteriorated at least by January
2000 when MRP transferred control over the common areas of the Riverfront Lofts
building to the Association. This defect made the Riverfront Lofts building not
"reasonably adequate" for "use and occupancy."
Reasonable adequacy for use and occupancy requires, at a minimum, an intact
structure. When conveyed, the facade was not intact. It had begun to chip off
and separate from the building. Other courts have found similar defects to have
breached the implied warranty of fitness. See Hills of Palos Condo. Ass'n, Inc.
v. I-Del, Inc., 255 Ill.App.3d 448, 193 Ill.Dec. 760, 626 N.E.2d 1311, 1326-27
(1993) (upholding jury verdict that spalling brick breached the implied
warranty); Elden v. Simmons, 631 P.2d 739, 741-42 (Okla.1981) (stating that
crumbling bricks could constitute breach); Roy E. Thomas Constr. Co. v. Arbs,
692 S.W.2d 926, 930-32 (Tex.App.1985) (stating that cracks in bricks and
foundation could constitute breach).
In addition, because of the spalling, the building was unsafe. Falling brick and
terra cotta posed a risk to pedestrians on the west side of the building and
caused the City of Milwaukee to cite the building for violating the City's
building code and to order that a canopy be installed. The violation charged was
not a minor one. The City charged that the building violated a code provision
requiring a building's exterior surfaces to be "reasonably weatherproof,
watertight ... [and] kept in a reasonably
good state of maintenance and repair." Milwaukee, Wis. Building Code § 275-32- 3
(2001). For this reason also, the building was not reasonably adequate for use
and occupancy.
Moreover, the
spalling affected not only the facade but compromised the
integrity of the building. The separation of the masonry from the building
permitted water to penetrate the building's structural frame. The facade's
defects, thus, were not minor but rather were substantial. See Stuart, 745 P.2d
at 1289-90 (stating that structural defects violate implied warranty).
Further, finding MRP liable for the defects in the facade furthers the purpose
of the statutory covenant. MRP renovated the building inside and out and was
thus in a better position than the buyers to discover and remedy the defects.
See Degnan, 696 P.2d at 433 ("The theory behind the implied warranty ...
recognizes that when either an innocent builder-vendor or an innocent buyer will
suffer, the builder-vendor, as the one in the better position to have prevented
the harm, shall be liable to the buyer for that harm."). In addition, the buyers
had a right to expect that they would obtain the benefit of their bargain--a
condominium unit in a building reasonably adequate to serve as a residence. The
buyers reasonably expected that the building would be safe and intact. Their
expectation imposed no unreasonable burden on the builder- vendor. Thus, a
finding of liability enforces the bargain that the parties struck. See Atherton
Condo. Apt.-Owners Ass'n, 799 P.2d at 259.
MRP argues that the implied covenant applies only to latent defects [FN7], and
that the facade's problems were not latent but, rather, were visible. Other
courts have held that implied warranties only apply to latent defects, meaning
those that would not be apparent to the average buyer after viewing the
property. See Redarowicz v. Ohlendorf, 92 Ill.2d 171, 65 Ill.Dec. 411, 441
N.E.2d 324, 330 (1982); Park v. Sohn, 89 Ill.2d 453, 60 Ill.Dec. 609, 433 N.E.2d
651, 656 (1982); Gupta v. Ritter Homes, Inc., 646 S.W.2d 168, 169 (Tex.1983);
Meadowbrook Condo. Ass'n, 565 A.2d at 240.
FN7. The Wisconsin Supreme Court has held that express warranties in real estate
contracts only cover latent defects. See Dittman v. Nagel, 43 Wis.2d 155,
161-62, 168 N.W.2d 190 (1969).
However, even assuming that the implied covenant applies only to latent defects,
MRP's argument fails because at the time of the conveyance the defects in the
facade were latent. Although parts of the facade were visible, the average
person would have been unable to conclude that substantial defects existed or
would soon exist. This is so for several reasons. First, the building sits close
to other buildings on its north and south sides, thus very little of the north
and south faces is visible from the ground level. Second, to the east of the
building is the Milwaukee River, thus the east face is only
visible from across the river at a considerable distance. Third, the building is
ten stories tall, and most of the facade's defects appeared high on the
building. (See Trial Ex. 21 photographs at 1-4.) Even on the west side, where
the view of the facade was unobstructed, the defects would not have been readily
visible to someone standing on the ground. Grothman indicated as much in the
Building Condition Survey when he recommended that MRP conduct a close- up
inspection. Finally, the average buyer, inexperienced in building construction,
would not have known that the cracked and chipped masonry that was visible was a
sign of a serious defect that affected the structural integrity of the building.
Thus, the defects in the facade are fairly characterized as latent.
MRP is liable to the Association for defects in the facade. The reasonable cost
to repair such defects was $154,157. Thus, the Association is awarded $154,157
less the $2,200 paid by MRP to the Association as a special assessment, or the
sum of $151,957.
b. Soundproofing
The Association also argues that MRP breached the implied covenant by
failing to install proper sound-proofing. I consider first whether MRP's work
was workmanlike and second, whether the lack of soundproofing made the property
not reasonably adequate for use and occupancy.
The Association has not shown by a preponderance of the evidence that MRP's
soundproofing failed to meet local industry standards and was, therefore,
unworkmanlike. Dossett testified that, while placing the demising walls on top
of the existing hardwood floors on floors five through seven resulted in easy
sound travel, this procedure was typical in the industry. Indeed, he stated that
he had never seen a builder renovating a structure with a hardwood floor do
otherwise. He also testified that resting the hardwood floor on sleepers was the
best way to construct a hardwood floor, and that it had little effect on the
transmission of impact noise. The Association offered no evidence rebutting
Dorsett's testimony. Thus, I conclude that the construction of the demising
walls and floors on floors five through seven was not unworkmanlike.
As for floors eight through ten, where there were no existing hardwood floors,
the Association established that MRP could have installed a sound-dampening pad
or possibly constructed the floors and demising walls differently. However, the
Association offered no evidence that local industry standards required MRP to do
so. Indeed, Dossett indicated that, at least with regard to the construction of
the floor, the sleeper system was preferable to any other and the amount of
soundproofing in the building was characteristic of that in buildings
constructed in a loft-style.
Plaintiff relies on the testimony of Yerges regarding the units' FIIC ratings to
demonstrate that the building fell below industry standards. However, the
question before me is not whether the condominium units were loud, but whether
MRP's construction was unworkmanlike. Yerges's testimony that some FIIC ratings
were lower than fifty-five does not, without more, show that MRP's performance
was unworkmanlike.
Plaintiff also showed that the sound of running water through pipes was
transmitted among the units. However,
Dossett testified that
MRP installed
rubber rings around the pipes to prevent the transmission of noise from pipes
hitting each other, but that there was no way to prevent the transmission of
noise from running water. The Association presented no evidence that local
industry standards required MRP to do more. Thus, the Association's claim based
on water noise is also rejected.
Next, I consider whether the alleged defects in sound-proofing made the building
not reasonably adequate for its intended use and occupancy. I conclude that
plaintiff has also not met its burden of proof on this issue. While the sound of
footsteps and running water may be annoying, it did not make the building
inadequate for use and occupancy as a residence. See Putnam v. Roudebush, 352
So.2d 908, 910 (Fla.Dist.Ct.App.1977) (holding that noise from an air
conditioner did not make building uninhabitable); Abrams v. Rapoport, 516 N.E.2d
943, 946 (Ill.App.1987) (holding that noises emanating from building roof
assembly during windy conditions did not make building uninhabitable). No
witness testified to the
contrary. Further, Dossett testified that the noise from footsteps was largely
ameliorated by a
carpet. Thus, the breach of implied covenant claim relating to the soundproofing
is rejected.
c. Inaccessible Air Conditioners
Next I address whether MRP breached the implied covenant by installing some
of the building's air conditioners so that they were inaccessible for cleaning,
maintenance and repair. The evidence indicated that the air conditioning units
on the second and fourth floors were installed only three to four inches apart
and were inaccessible for even routine cleaning. Further, the evidence showed
that the air conditioning units on floors five through ten, although accessible
for routine cleaning, are not accessible for maintenance and repair. This is so
because the air conditioners were placed on top of drywall or tile ceilings that
contained no access panels.
Generally, expert testimony is needed to determine whether a manner of
construction meets with industry standards and is, thus, workmanlike. See Herkert v. Stauber, 106 Wis.2d 545, 570, 317 N.W.2d 834 (1982). However, when an
issue can be resolved by common sense, no such testimony is needed. Id. Here,
the Association offered no expert testimony regarding industry standards of air
conditioner installation.
However,
Karoly testified that air conditioning units should be cleaned
annually. Thus, common sense instructs that installation which makes such
foreseeable cleaning impossible is not workmanlike. Counsel for
MRP even
acknowledged in his closing statement that the configuration of the air
conditioners on the second and fourth floors was "a problem." Therefore,
MRP's
installation of the units on floors two and four was not workmanlike and
breached the implied covenant.
Finding that MRP is liable for improperly installing these air conditioners
serves the purpose of § 706.10(7). The unit owners reasonably expected that the
air conditioners would be accessible for foreseeable cleaning. Requiring that
MRP's work satisfy this expectation imposes no unreasonable burden. MRP should
have known of and corrected this problem, thus a finding of liability enforces
the standard of ordinary care that the parties contemplated in striking their
bargain.
The units on floors five through ten, which are accessible for cleaning,
are another matter. The record contains no evidence as to whether or when such
units will likely need maintenance and repair. Thus, the Association has not
proven that the need for access is foreseeable; and common sense does not compel
me to find that MRP's failure to install access panels to permit such access was
unworkmanlike. The record further contains no evidence that the absence of such
panels makes the property inadequate for use and occupancy. Therefore, the
Association's claim based on the failure to install access panels is rejected.
MRP argues that it cannot be held liable for the inaccessibility of
any of the air conditioners because they are part of the individually-owned
condominium units, not the common elements, and because the Association has not
proven that the affected condominium unit owners are in privity of contract with
MRP. [FN8] I conclude,
however, that under the circumstances of this case, the state supreme court
would not hold that the Association could recover damages only for defects that
affected units whose owners were in privity with MRP.
FN8. MRP previously raised a privity argument in response to the Association's
claims for damages resulting from defects in the common areas. Specifically, MRP
argued that the Association could only recover damages in an amount proportional
to the percentage of the common areas owned by residents in privity of contract
with MRP. However, I previously determined that Wisconsin law permitted the
Association to recover 100% of the damages to common areas.
The evidence does not make clear which condominium units were affected by the
installation problems. Concerning the air conditioners that were installed too
close together, Karoly testified that the air conditioners themselves were on
floors two and four, and that the problem affected twelve units. Each floor in
the building has four units, thus, although the air conditioners themselves were
on floors two and four, the units
affected were on floors two, three and four. When plaintiff commenced this suit,
two of the units had been resold. (Trial Ex. 117.) Thus, it appears that two of
the owners on whose behalf the Association brought this action are not in
privity of contract with MRP.
Neither the language nor the purpose of § 706.10(7) suggests that the
statutorily implied warranties cover only conveyances where the buyer and
builder-vendor are in privity of contract. Like original buyers, subsequent
buyers also rely on builders' superior knowledge and expertise relating to the
structures that they construct and reasonably expect that their performance will
be workmanlike. See Redarowicz, 65 Ill.Dec. 411, 441 N.E.2d at 330 ("The purpose
of the warranty is to protect purchasers' expectations by holding
builder-vendors accountable; we do not believe it is logical to arbitrarily
limit that protection to the first purchaser of a new house."); Terlinde v.
Neely, 275 S.C. 395, 271 S.E.2d 768, 769 (1980) ("The fact that the subsequent
purchaser did not know the home builder, as did the original purchaser, does not
negate the reality of the 'holding out' of the builder's expertise and reliance
which occurs in the market place."); Moxley v. Laramie Builders, Inc., 600 P.2d
733, 736 (Wyo.1979) ("[A]ny reasoning which would arbitrarily interpose a first
buyer as an obstruction to someone equally as deserving of recovery is
incomprehensible."). Indeed, limiting a builder's liability
according to how long the first buyer chooses to own the property would be
arbitrary in light of the frequency with which people can be expected to move
from one house to another. Redarowicz, 65 Ill.Dec. 411, 441 N.E.2d at 330
(holding that warranty should extend to subsequent purchasers in part because "[w]e
are an increasingly mobile people").
In addition, in the present case it is reasonable not to impose a privity
limitation because so little time passed between the initial conveyances and the
resale of certain units. The units were first conveyed in 1998 and 1999 and
resold in December 1999. [FN9] (See Trial Ex. 117.) It is not unreasonable to
hold a builder responsible for performance that was unworkmanlike when the
deficiency was discovered so soon after completion, regardless of who holds
title to the property. See Redarowicz, 65 Ill.Dec. 411, 441 N.E.2d at 330
(stating that "[t]he compelling public policies underlying the implied warranty
of habitability should not be frustrated because of the short intervening
ownership of the first purchaser" and finding a time period of approximately one
year insufficient to bar a claim by a subsequent purchaser).
FN9. I consider only those sales which occurred before 2001 when Iron Fireman
discovered the problem and moved the air conditioners because the Association
brought the claim in order to recover for the costs it incurred
during this period.
Further, the Wisconsin Supreme Court has permitted recovery where there was no
privity of contract in analogous situations when public policy concerns
suggested that permitting recovery was appropriate. For example, in A.E.
Investment
Corp. v. Link Builders, Inc., 62 Wis.2d 479, 488, 214 N.W.2d 764 (1974), the
court held that an architect who was negligent in designing a building could be
liable to a third party with whom the architect was not in privity. See also
Citizens State Bank v. Timm, Schmidt & Co., S.C., 113 Wis.2d 376, 385, 335
N.W.2d 361 (1983) (holding that a certified public accounting firm could be
liable for errors in an audit to a third party with whom the firm was not in
privity).
Finally, the trend in the case law is to find that the implied warranty of
habitability and workmanlike performance can be enforced by subsequent
purchasers. See Sean M. O'Brien, Caveat Venditor: A Case for Granting Subsequent
Purchasers a Cause of Action Against Builder-Vendors for Latent Defects in the
Home, 20 J. Corp. L. 525, 534 (1995) ("Currently, at least fourteen states
extend the implied warranty of habitability to subsequent purchasers."); Robert
L. Cherry, Jr., Builder Liability for Used Home Defects, 18 Real Est. L.J. 115,
138 (1989) (noting that in the twelve years following the first decision
extending the warranty to subsequent buyers,
Barnes v. Mac Brown & Co., Inc., 264 Ind. 227, 342 N.E.2d 619 (1976), seventeen
jurisdictions have followed); see also Redarowicz, 65 Ill.Dec. 411, 441 N.E.2d
at 330 (noting that the Uniform Land Transactions Act extends the implied
warranty to subsequent purchasers); Lempke v. Dagenais, 130 N.H. 782, 547 A.2d
290, 293-94 (1988) (collecting cases from other jurisdictions); Nichols v. R.R.
Beaufort & Assocs., Inc., 727 A.2d 174, 179 (R.I.1999); Gupta, 646 S.W.2d at
169.
The parties have stipulated that it cost $12,100 to reconfigure the air
conditioners on the second and fourth floors. Thus, I will award plaintiff
damages in this amount.
d. Construction Dust and Debris
The Association's claim with regard to MRP's failure to clean up
construction dust and debris will be rejected. The Association offered no
evidence of industry standards regarding construction clean-up and failed to
show how the debris comprised the use and occupancy of the building. Thus, the
Association has not met its burden of showing either that MRP's performance was
unworkmanlike or that the dust and debris made the building inadequate.
C. Whether Covenant Was Disclaimed
MRP argues that even if its construction was unworkmanlike or caused the
building to not be reasonably adequate, it cannot be held liable because in
several documents provided to condominium owners it disclaimed liability.
Under § 706.10(7) a covenant shall be implied "[i]n the absence of an express or
necessarily implied provision to the contrary." Thus, the question presented is
whether the language in the documents on which MRP relies constituted an express
or necessarily implied provision to the contrary of implying a covenant.
In predicting how the state supreme court would answer this question, I begin
with the words of the statute. "[E]xpress" means "directly and distinctly stated
... not dubious or ambiguous." Webster's Third New International Dictionary 803
(3d ed.1986). "[N]ecessarily" means "in such a way that it cannot be otherwise
... inevitably, unavoidably." Id. at 1510. "[C]ontrary" means "diametrically
different[,] ... opposite in character or nature ... mutually opposed." Id. at
495. Therefore, an express or necessarily implied provision to the contrary is a
direct, distinctly-stated, unambiguous provision stating that the covenant is
not to be implied, or a provision that inevitably or invariably
leads to the conclusion that the covenant is not to be implied.
Thus, the statute requires courts to imply the covenant unless there is a clear,
unmistakable and unambiguous disclaimer. This rule is consistent with the law in
most other states. A majority of states require disclaimers of implied
warranties in new home sales to be "specific and unambiguous." See David L.
Abney, Disclaiming the Implied Real Estate Common-Law Warranties,
17 Real Est. L.J. 141, 142-43 (Fall 1988) ("The majority rule is clear in
stating that a disclaimer must be specific and unambiguous in order to be
effective"); see, e.g., See Starfish Condo. Ass'n v. Yorkridge Serv. Corp., 295
Md. 693, 458 A.2d 805, 810 (1983) (finding "as is" provision insufficient to
waive implied warranty of habitability because provision did not expressly name
the warranty).
The statute thus establishes a high standard for defendants relying on
disclaimers. "To allow an easy disclaimer ... would place the buyer right back
in the same position as having no implied [covenant] protection at all." Abney,
supra, at 142. The legislature could not have intended this result. See id. at
142-51 (discussing the high standards courts have set for disclaiming implied
warranties in new home sales). I consider each of MRP's three alleged
disclaimers to determine whether it is sufficient.
First, MRP points to a document dated December 5, 1997, which was provided to
purchasers with the condominium disclosure materials and Building Condition
Survey prior to closing. This document stated as follows:
As required by Section 703.33(2)(cm) of the Wisconsin Condominium Ownership Act
with respect to conversion condominiums, the undersigned, being the Declarant of
Riverfront Lofts Condominium, makes the following statements to each purchaser
of a unit in Riverfront Lofts Condominium:
1. The present condition of those structural components and mechanical and
electrical installations that are material to the use and enjoyment of the
building in which the units in the Condominium are located is as set forth in
the attached Building Condition Survey made by the independent engineering firm
of Graef, Anhalt, Schloemer & Associations, dated December 1, 1997.
2. No representations are made by the Declarant regarding the expected useful
life of any of the items described in the attached Building Condition Survey.
3. There are no uncured violations of building code or other municipal
regulations with respect to the Condominium.
(Trial Ex. 110.) Specifically, MRP argues that the language in the second point
constituted a valid disclaimer of the defects in the facade and of the improper
installation of the air conditioners.
For several reasons, the Wisconsin Supreme Court would be unlikely to conclude
that the statement on which MRP relies was sufficiently specific and unambiguous
to constitute a valid disclaimer. First, the language did not "express[ly]"
state that the covenant would not be implied because it did not mention the
covenant. Further, the statement did not "necessarily impl[y]" that a covenant
would not be implied because it did not address the matters covered by the
covenant. Rather, it concerned a related but different issue than those
addressed by the covenant. The language in point two addressed "the expected
useful life" of the parts of the building described in the Building Condition
Survey; whereas, the covenant addresses the workmanlike manner of the builder's
performance and the adequacy of the
structure for certain uses. Nothing in the language of point two would have
inevitably led to the conclusion that MRP was disclaiming its statutory
obligations to perform in a workmanlike manner or to make the building
reasonably adequate for use and occupancy.
Nor did the Building Condition Survey, which point two references, clearly and
unambiguously disclaim the implied covenant. The Survey referred to the facade
and the air conditioners but did not alert buyers to their defects. Thus, it
also did not imply, much less "necessarily impl[y]" that the statutory covenant
warranting that the building was not defective was being disclaimed. With regard
to the facade, the Building Condition Survey described what Grothman could see
and concluded that further inspection was necessary to determine whether there
were significant problems. It did not describe the condition of the facade at
that time with any degree of certainty, nor convey that it had serious
structural defects. (See Trial Ex. 2 at 3-3, 3-5 to 3-7.) Thus, with regard to
the facade, the survey did not disclaim the covenant.
With regard to the air conditioners, the Survey stated that they were "in good
working order and require[d] no modifications," but it said nothing about how
they were installed or whether they were accessible for maintenance and repair.
(Id. at 4-2.) Thus, the Survey did not alert buyers to the fact that they were
improperly installed on floors two and four and, therefore, cannot
reasonably be characterized as a disclaimer of the statutory covenant warranting
proper installation.
For the foregoing reasons, the language in point two of the condominium
disclosure materials did not expressly or necessarily imply that the statutory
covenant was being disclaimed.
The result would be the same under standards governing disclaimers developed by
courts in other jurisdictions. Some courts hold that general disclaimers waiving
all warranties are invalid. E.g., Wawak, 449 S.W.2d at 926 (finding general
language waiving all warranties insufficient to disclaim implied warranty of
habitability). The statement in point two related to the entire property which
is referenced in the Building Condition Survey. Thus, even if the statement
could be construed as a disclaimer, it was so general that it probably would be
found invalid under the Wawak standard.
Other courts hold that disclaimers containing boilerplate language are invalid.
Petersen, 27 Ill.Dec. 746, 389 N.E.2d at 1159; Crowder, 564 S.W.2d at 881 n. 4.
The statement in point two consisted solely of boilerplate language taken from
Wisconsin's condominium disclosure statute. See Wis. Stat. § 703.33(2)(cm).
Some jurisdictions permit disclaimers only if the builder-vendor can show that
the buyer actually knew of the defects, knew that the warranty was being
disclaimed and knew the consequences of its exclusion. See Belt v. Spencer,
41 Colo.App. 227, 585 P.2d 922, 925 (1978); Petersen, 27 Ill.Dec. 746, 389
N.E.2d at 1159 (same); Crowder, 564 S.W.2d at 881 n. 4; Centex Homes, 2001 WL
1946128, at *7. MRP offers no such evidence here.
The second document which MRP claims included a disclaimer was the addendum
to the offers to purchase. It stated that, "Seller [MRP] shall, at Seller's
expense remedy any defects in workmanship or materials related to the Property
for a period of one (1) year from the date of closing, provided Buyer gives
written notice to Seller of any claimed defects within such one (1) year period.
Construction industry standards shall be used to determine if any defects
exist." (See Trial Ex. 1 ¶¶ 11 or 13.)
However, this representation
does not meet the high statutory standard for disclaiming the covenant. The
representation did not mention the covenant, thus, it did not "express[ly]"
disclaim it. Further, the representation did not necessarily imply that the
covenant was being disclaimed because it was compatible with the covenant rather
than mutually exclusive.
A builder can warrant that it will repair defects discovered within one year of
sale without disclaiming a promise that its performance will be workmanlike and
that the building will be reasonably adequate when it is conveyed. The promise
to make repairs does not preclude the promises implied by law. Indeed, the
majority of courts to address this issue have concluded that "the presence of an
express warranty is an added guarantee inserted into
the contract to extend, rather than limit, liability for faulty construction"
and, thus, does not disclaim implied warranties. Bridges v. Ferrell, 685 P.2d
409, 411 (Okla.App.1984) (citing Burton-Dixie Corp. v. Timothy McCarthy Constr.
Co., 436 F.2d 405 (5th Cir.1971); Hoagland v. Celebrity Homes, Inc., 40 Colo.App.
215, 572 P.2d 493 (1977); Rapallo S., Inc. v. Jack Taylor Dev. Corp., 375 So.2d
587 (Fla.Dist.Ct.App.1979); Norair Eng'g Corp. v. St. Joseph's Hosp., Inc., 147
Ga.App. 595, 249 S.E.2d 642 (1978); Richman v. Watel, 565 S.W.2d 101
(Tex.Civ.App.1978), aff'd, 576 S.W.2d 779 (Tex.1978) (expressly declining to
reach the issue)); accord Hennes Erecting Co. v. Nat'l Union Fire Ins. Co., 813
F.2d 1074, 1081 (10th Cir.1987); Cafro v. Brophy, No. CV 9557138S, 1998 WL
279943, at *11 (Conn.Super. May 12, 1998), rev'd on other grounds by 62 Conn.App.
113, 774 A.2d 206 (2001); see also Gilbane Bldg. Co. v. Ocean State Bldg. &
Wrecking, Inc., 748 A.2d 826, 828 (R.I.2000).
Third, MRP argues that the integration clause in the offers to purchase
expressed or necessarily implied that the statutory covenant would not be
implied. The offers stated that they contained "the entire agreement of the
Buyer and Seller regarding the transaction. All prior negotiations and
discussions have been merged into this Offer." (Trial Ex. 16 at 3.) However,
this language did not disclaim the covenant. Like the provisions discussed
above, it did not mention the covenant and, thus, did not expressly disavow it.
Further, it did not impliedly disclaim the covenant because the covenant applies
by operation of law not as the result of "prior negotiations and discussions."
Even assuming that the implied covenant was part of the parties' prior
negotiations and discussions, the integration clause did not clearly and
unambiguously disclaim it.
Other courts that have addressed the issue have concluded that an integration
clause does not bar a claim for breach of an implied warranty. See Griffin v.
Wheeler-Leonard and Co., Inc., 290 N.C. 185, 225 S.E.2d 557, 567-68 (1976)
(addressing agreement between home builder-seller and buyer); Tyus v. Resta, 328
Pa.Super. 11, 476 A.2d 427, 434-35 (1984) (same); Melody Home Mfg. Co. v.
Barnes, 741 S.W.2d 349, 355 (Tex.1987) (same); see also U.S. Gypsum Co. v.
Schiavo Bros., Inc., 450 F.Supp. 1291, 1304 (E.D.Pa.1978) (addressing
commercial-landlord tenant relationship), aff'd on this issue by 668 F.2d 172,
175-76 (3d Cir.1981).
For the foregoing reasons, none of the documents relied on by MRP constituted an
"express or necessarily implied provision to the contrary" of the statutory
language making the covenant part of the parties' agreement. [FN10]
FN10. Even if one of the documents on which MRP relies did constitute a valid
disclaimer of the implied covenant, MRP would arguably be liable under the
provision in the addenda requiring it to repair defects
discovered within one year of closing. This provision was included in every
conveyance and at least five conveyances closed within one year of the discovery
of the defects in the facade. The record does not indicate on exactly what date
the Association asked MRP to perform the facade repair work but does reveal that
the request came sometime between September 22, 2000 when the City issued a
notice of violation and January 2001 when Thomas Holton inspected the building.
Sales of condominium units closed on February 28, March 29 and 30, April 17 and
September 1, 2000. (Trial Ex. 117.) However, I need not address this issue
because I find that MRP did not disclaim the implied covenant, and because the
parties have not addressed it.
III. DAMAGES FOR BREACH REGARDING HALLWAYS AND STAIRWELLS
Lastly, I address the Association's damages for MRP's failure to
complete work in the hallways and stairwells as required by the Krawczyk closing
agreement. A plaintiff has the burden to prove damages "with a reasonable degree
of certainty." Mgmt. Computer Servs., Inc. v. Hawkins, Ash, Baptie & Co., 206
Wis.2d 158, 189, 557 N.W.2d 67 (1996). The evidence of damages must be
sufficient to enable the fact-finder "to make a fair and reasonable
approximation." Id.
The only evidence in the record with respect to the cost of completing the
unfinished work identified in the agreement appears in the agreement itself.
House Doctor's lump sum bid for unspecified work is insufficiently specific to
help me determine the cost of completing the work described in the agreement.
The Association urges me to rely on Dossett's testimony that he thought that he
had estimated the cost of finishing the stairway landings and painting the walls
at $40,000. However, Dossett admitted that he could not recall with certainty
what he bid. In addition, it is not clear that Dossett's estimate covers the
same work as that required by the Krawczyk closing agreement. The latter
required MRP to "complete main and east stairwells including floors, trim and
walls," remove a telephone box and wiring and clean the slate stairs at an
estimated cost of $3,000. (Trial Ex. 4 ¶ G.) The difference between the $3,000
listed in the contract and Dossett's estimate is so great as to suggest that the
parties may not have been talking about the same work. Thus, Dossett's testimony
is also insufficiently certain to provide a basis for assessing damages. I am
left with the amounts listed in paragraphs F, G and H of the Krawczyk closing
agreement. I will award the Association damages totaling $8,000 based on those
figures.
IV. CONCLUSION
THEREFORE, THE COURT FINDS defendant Milwaukee / Riverfront Properties L.P.
liable to plaintiff Riverfront Lofts Condominium Owners Association for breach
of the covenant implied by Wis. Stat. § 706.10(7) with respect to defects in
the facade and in the installation of air conditioners on the second and fourth
floors. Plaintiff's breach of implied covenant claims with respect to defects in
soundproofing, in the installation of air conditioners on the fifth through
tenth floors and in the clean-up of construction debris are rejected.
IT IS ORDERED that defendant pay to plaintiff damages as follows:
The amount of $151,957 for defects in the building facade;
The amount of $12,100 for installing air conditioners too close together on the
second and fourth floors; and
The amount of $8,000 for completion of the work described in paragraphs F, G and
H of the Krawczyk closing agreement.
FINALLY, IT IS ORDERED that the Clerk of Court enter judgment for plaintiff
and against defendant in the amount of $172,057.
End
|