
|
|
|
United States Court
of Appeals,Federal Circuit.
INTERNATIONAL
TECHNOLOGY CORPORATION, Appellant,
v.
Donald C. WINTER,
Secretary of the Navy, Appellee.
No. 2007-1276.
April 18, 2008.
Appeal from the Armed Services Board
of Contract Appeals in no. 54136, Administrative Judge Jack Delman.
Peter B. Jones, Jones & Donovan, of
Newport Beach, CA, argued for appellant.
David M. Hibey, Trial Attorney,
Commercial Litigation Branch, Civil Division, United States
Department of Justice, of Washington, DC, argued for appellee. With
him on the brief were Jeanne E. Davidson, Director, and Deborah A.
Bynum, Assistant Director.
Before LINN, DYK, and MOORE, Circuit
Judges.
Opinion for the court filed by Circuit
Judge DYK.
Circuit Judge MOORE concurs in the
result.
DYK, Circuit Judge.
This case
involves a claim for breach of a cost-plus-fixed-fee contract for
treatment of contaminated soil at a Navy facility in Stockton,
California. The contractor, International Technology Corporation
(“ITC”),FN1 seeks to recover additional soil treatment
expenses incurred by a subcontractor, Terra Kleen Response Group,
Inc. (“TK”), because of unexpectedly high concentrations of clay in
the treated soil. The Armed Services Board of Contract Appeals
(“Board”) held that ITC was not entitled to an award of costs and
also determined that ITC was not entitled to damages for breach of
the contract. We affirm.
BACKGROUND
ITC was awarded a cost-plus-fixed-fee
contract on February 23, 1994, by the Department of the Navy. The
contract was for environmental remediation services designed to remove
pesticides and related chemicals at a variety of contaminated sites. The
contract did not describe the services to be performed, but instead
provided that services would be specified in a series of subsequent
delivery orders. Because the contract was awarded on a
cost-plus-fixed-fee basis, the contract contained the “Limitation of
Cost” provision of Federal Acquisition Regulation (“FAR”) 52.232-20, 48
C.F.R. § 52.232-20. Pursuant to this clause, “the estimated cost shown
in the contract constitutes a ceiling on the government's contractual
liability,” which can only be increased if the government modifies the
cost ceiling. Advanced Materials, Inc. v.
Perry, 108 F.3d 307, 310 (Fed.Cir.1997). In the absence of such a
modification, “the contractor is not required to continue performance or
incur costs that exceed those estimated in the contract.”Id. The
Limitation of Cost clause also contains a notice provision, requiring
“that the contractor notify the government in writing when it
anticipates that within the next sixty days it will exceed seventy-five
percent of the estimated cost and provide a revised estimate.”Id.
The delivery order relevant to this case,
Delivery Order number 102 (“the DO”), was issued by the government on
August 29, 1997. It called for treatment of pesticide-contaminated soil
at the Naval Communication Station in Stockton, California. The DO also
provided that the period of performance was September 1, 1997, through
September 30, 1998, and stated an estimated cost, for purposes of the
Limitation of Cost clause, in the amount of $1,228,409.FN2On
approximately April 17, 1998, ITC awarded a fixed-price subcontract to
TK to perform the soil treatment at the Stockton worksite.
TK
had developed a solvent extraction technology for the removal of certain
contaminants, including the pesticide DDT, from contaminated soil, and
had earlier demonstrated its technology in a small-scale pilot soil
treatment program at the Stockton worksite itself. The solvent
extraction technology works by dissolving certain contaminants from the
soil into a solvent in sealed treatment bins. The solvent is then
drained and filtered to remove the contaminants, so that the solvent can
be reused. Two reports, entitled Terra Kleen
Solvent Extraction Technology Evaluation
Report (“Solvent Technology Report”) and Focused
Feasibility Study for DDT-Contaminated Soil
(“Feasibility Study”), prepared by a third-party contractor, discussed
and evaluated the results of TK's pilot treatment program. TK provided
technical input used in the preparation of both reports.
The Solvent Technology Report and the
Feasibility Study were not prepared pursuant to the government contract
involved here. However, the DO briefly referenced these reports. One
section of the DO presented a series of “specific tasks” the contractor
should perform, each followed by descriptive paragraphs. The first of
these tasks was entitled “Examine Existing Documents.” It directed the
contractor to “[e]xamine the following documents:” and then listed the
Feasibility Study and the Solvent Technology Report. Appellant's
Supplemental App., tab 2, at 5. This provision also contained the
following note: “The contractor is not required to provide written
responses to these documents. Examining these items will assist the
contractor in preparing the plans described in task 2 of this delivery
order.”Id. FN3
A key focus in this case has been the
content of the two reports, and in particular what they represented
about the clay content of the soil at the site. The Solvent Technology
Report described the Stockton site, TK's solvent extraction technology,
the procedures used, and the results of the pilot study. A single,
one-page figure in this report, Table 2-15, entitled “Soil
Characteristics,” presented characteristics for nine soil samples taken
from the site during the pilot treatment program, including the
classification of the soil type for each and the percent of sand, silt,
clay, and gravel in each. For the nine samples, the clay content figures
reported in Table 2-15 were: 6%, 7%, 9%, 9%, 9%, 9%, 11 %, 10%, and 8%.
TK's President and CEO, Alan Cash, was present and observed the manner
in which at least six of these soil samples were collected. The Solvent
Technology Report also indicated:
Solvent extraction cycles took much longer
than expected due to the reduced [soil] permeability, thereby increasing
treatment time and cost.... The soil also tended to form clay lumps when
compacted. This resulted in the formation of soil aggregates which were
difficult to saturate with solvent, resulting in less particle contact
and lower DDT removal efficiencies.
Appellant's Supplemental App., tab 1, at
3-4.
The Feasibility Study compared the
relative merits of several alternative methods for treatment or disposal
of the contaminated soil at the Stockton site, including use of TK's
solvent extraction technology. The appendix of the Feasibility Study
included a number of tables reporting analyses of samples of the
contaminated Stockton soil before and after TK treated the soil in the
pilot program. These tables referenced the soil composition, and
indicated that some samples had a majority of clay, that is,
substantially higher clay content than the figures in the Solvent
Technology Report. It is unclear whether the samples reported in the
Feasibility Study were the same as the samples reported in the Solvent
Technology Report.
Pursuant to its
subcontract with ITC, TK used its solvent extraction technology to treat
the soil at the Stockton worksite. However, TK experienced problems in
treating the contaminated soil. In a progress report to the government
dated February 2, 1999, ITC noted that processing of the first increment
of soil had been delayed, and attributed the delay in part to higher
than expected levels of clay in the soil. TK took samples from soil in
its treatment bins and from the stockpile of untreated contaminated soil
for independent laboratory analysis of clay levels. The clay levels
indicated for these samples ranged between approximately 23.2% and
28.8%, considerably higher than the clay content for the nine samples
listed in the Solvent Technology Report, though less than some samples
described in the Feasibility Study.
All work under the DO at the Stockton site, including demobilization, was completed during the week of June 26, 2000. The government accepted the project as complete on June 30, 2000. During its performance under the subcontract, TK first made ITC aware of the problems associated with clay in March 1999, but submitted to ITC a request for equitable adjustment based on the high clay content of the soil for the first time on November 15, 1999.
Although ITC
had not provided compensation to its subcontractor, on its claim for an
equitable adjustment, on January 3, 2001, ITC made a formal request to
the government for an equitable adjustment, seeking compensation to
cover TK's claim for equitable adjustment under the subcontract. In
November 2001, ITC revised its claim to request $965,347 for expenses
under the subcontract, and an additional $216,188 for ITC's own
expenses, apparently representing ITC's efforts to investigate and
substantiate TK's claim. The Contracting Officer (“CO”) issued a final
decision denying ITC's claim on February 28, 2003. The CO concluded that
ITC was not entitled to any equitable adjustment under the contract,
because the cost would exceed the total cost under the Limitation of
Cost clause, and ITC had not followed the notice procedures under that
clause or obtained a modification to cover these expenses before
incurring them.
ITC appealed this determination to the
Board. After a hearing, the Board issued a decision, dated July 20,
2006, denying ITC's appeal. The Board found that ITC's requested
adjustment would exceed the cost ceiling of the Limitation of Cost
clause and concluded that ITC had not met its burden to prove either
that it complied with that clause's requirement to notify the government
before exceeding the cost ceiling, or that ITC was excused from doing so
because the cost was unforeseeable. The Board also concluded that ITC
would not be excused from providing the notice required by the
Limitation of Cost clause just because the costs associated with TK's
request for equitable adjustment were uncertain and subject to ITC's
investigation at the time ITC first became aware of them.
Finally, the Board rejected ITC's
alternative argument that the government had breached the DO by
inaccurately describing the clay content of the contaminated soil at the
Stockton site. First, the Board determined that neither the Solvent
Technology Report, the Feasibility Study, “nor any DO provisions
generally warranted soil content or soil conditions at the Stockton
sites, nor warranted a low clay content of the soil. Indeed, both
reports, when read as a whole, reflect information showing that certain
soil samples were of relatively high clay and silt content.”J.A. at 27.
The Board also concluded that TK could not have been misled about the
soil conditions because TK “earlier treated the soil from these same
sites in the pilot study,” and the Solvent Technology Report “indicated
that TK had difficulties with low permeability of soil and with the clay
at the sites at that time.”Id. The Board determined that a breach
claim requires, among other things, a showing of “government
culpability” and concluded that ITC had not made such a showing:
Misrepresentation in the contractual
context constitutes a knowing or negligent untrue representation of fact
or failure to disclose, requiring proof of government culpability beyond
showing a mere variation between conditions stated in the contract and
those actually encountered. [ITC] failed to make a case of
misrepresentation on this record.
Id. at 28 (citing Foster
Constr. C.A. v. United States,
193 Ct.Cl. 587, 435 F.2d 873, 880-81 (Ct.Cl.1970)).
ITC timely appealed the Board's decision,
and we have jurisdiction pursuant to 28 U.S.C. § 1295(a)(10). We review
legal conclusions of the Board, including its construction of contract
provisions, without deference, and accept its factual determinations
“unless they are ‘fraudulent, or arbitrary, or capricious, or so grossly
erroneous as to necessarily imply bad faith, or if such decision is not
supported by substantial evidence.’ “ England v. Contel
Advanced Sys., Inc., 384 F.3d 1372, 1377
(Fed.Cir.2004) (quoting E.L. Hamm & Assocs.
v. England, 379 F.3d 1334, 1338 (Fed.Cir.2004)).
DISCUSSION
When this case was before the Board, ITC sought to recover TK's
additional costs (and its own related costs) as a cost under the
contract. The Board rejected this claim because ITC had not complied
with the notice and approval provisions of the Limitation of Cost
clause. We do not understand ITC to challenge this holding on appeal. In
any event, the Board was correct that ITC cannot recover under a cost
theory because of ITC's failure to comply with the notice provisions of
the Limitation of Cost clause.
ITC instead urges on appeal that it has a
valid pass-through claim for breach of contract. ITC asserts that the
government inaccurately represented the site conditions in the DO and
that TK relied on this representation in bidding on the subcontract. ITC
contends that it is liable to TK under the fixed price subcontract and
that the government is liable to ITC on a pass through basis. ITC does
not argue that it reasonably relied upon and was misled by any
representation in its cost-plus-fixed-fee contract with the government.
I
A
pass-through claim allows a prime contactor to assert against the
government a claim for harm caused by the government to a subcontractor
where the subcontractor could hold the prime contractor liable for that
harm. “In a pass-through suit, a prime contractor that is liable for
damages sustained by its subcontractor may bring claims against the
government on behalf of the subcontractor.”Metric
Constructors v. United States, 314 F.3d 578,
581 (Fed.Cir.2002).See generally John Cibinic, Jr. et al.,
Administration of Government Contracts
676-77 (4th ed.2006) (describing pass-through claims and the Severin
doctrine that governs the allowance of pass-though claims). If the prime
contractor is liable “to the subcontractor for the damages sustained by
the latter[ ]” caused by the government's action, the prime contractor
can “show injury to it from the government's action,” and there is no
basis for the government to object to the subcontractor's claim due to
lack of privity. E.R. Mitchell Constr. Co.
v. Danzig, 175 F.3d 1369, 1370 (Fed.Cir.1999). A typical
example of a pass-through claim is a claim by a subcontractor, under
fixed-price prime and sub contracts, for government-caused delay that
resulted in increased indirect overhead costs for the subcontractor.
See id. at 1370-72.
None of the cases called to our attention,
however, deals with pass-through claims similar to the claim asserted
here. ITC's pass-through theory in this case presents a number of
difficulties, including (1) whether a subcontractor pass-through claim
can be based on representations appearing in the prime contract and (2)
whether the Limitation of Cost clause limits the prime contractor's
ability to assert a pass-through claim based on breach of the
subcontract. We need not decide these issues, for we conclude that ITC
would not prevail in this case even if all of these issues were resolved
in its favor.
II
ITC contends that the government breached
the DO by incorrectly representing the amount of clay in the
contaminated soil, and that TK relied on this representation to its
detriment in formulating its subcontract bid. ITC explains that the DO
referenced the Solvent Technology Report, which in turn reported
significantly lower clay content for certain soil samples than the clay
levels that TK actually encountered in the contaminated soil while
performing under the subcontract. Mr. Cash testified that he relied on
the clay content figures in Table 2-15 of the Solvent Technology Report
in preparing TK's subcontract proposal, and TK's proposal stated that
“Terra-Kleen has assumed that the contaminated soil contains an overall
clay content of less than 10% clay.”J.A. at R4 202.19.
A misstatement as to site conditions in a
government contract can support a claim for breach of contract. See
Hollerbach v. United States, 233 U.S. 165,
172, 49 Ct.Cl. 686, 34 S.Ct. 553, 58 L.Ed. 898 (1914). The same
requirements apply whether the contractor asserts such a common law
breach claim or a Type I claim under the Differing Site Conditions
clause, a clause which is common in government construction contracts,
but was not included in ITC's contract with the government.FN4Compare
T. Brown Constructors, Inc. v.
Pena, 132 F.3d 724, 728-29 (Fed.Cir.1997) (listing elements for
common law breach claim) with Renda Marine, Inc.
v. United States, 509 F.3d 1372, 1376
(Fed.Cir.2007) (listing elements for Type I differing site conditions
claim).See also P.J. Maffei Bldg.
Wrecking Corp. v. United States, 732
F.2d 913, 919 (Fed.Cir.1984) (applying the same analysis to a common law
breach claim and a Type I differing site condition claim).
In
order to prevail on such a site conditions claim, a contractor must
establish four elements. First, the contractor must prove that a
reasonable contractor reading the contract documents as a whole would
interpret them as making a representation as to the site conditions.
See Renda Marine, 509 F.3d at 1376 (“[A] contractor
must first prove, as a threshold matter, that the contract contained
some identification of the conditions to be encountered at the site.”);
H.B. Mac, Inc. v. United States,
153 F.3d 1338, 1345 (Fed.Cir.1998) (explaining that the court “place[s]
itself into the shoes of a reasonable and prudent contractor and
decide[s] how such a contractor would act in interpreting the contract
documents”). This is a question of contract interpretation reviewed de
novo on appeal. H.B. Mac, 153 F.3d at 1345.
Second, the contractor must prove that the actual site conditions were not reasonably foreseeable to the contractor, with the information available to the particular contractor outside the contract documents, i.e., that the contractor “reasonably relied” on the representations. Renda Marine, 509 F.3d at 1376 (“[T]he contractor must demonstrate that the conditions encountered were not reasonably foreseeable in light of all information available to the contractor when bidding [and] that the contractor reasonably relied upon its original interpretation of the contract.”). This issue is factual in nature, and review is deferential. See id. at 1378.
Third, the
contractor must prove that the particular contractor in fact relied on
the contract representation. See id. at 1376.Again, this
is a fact issue reviewed under a deferential standard. See id.
at 1378.
Fourth, the
contractor must prove that the conditions differed materially from those
represented and that the contractor suffered damages as a result, which
is again a fact question. See id. at 1376.FN5
We conclude
that the contractor here cannot satisfy either the first or second of
these requirements.
A
We note first that ITC was required to
demonstrate that a reasonable contractor would read the contract
documents as representing that the contaminated soil contained less than
ten percent clay. See Renda Marine, 509 F.3d at
1376 (citing H.B. Mac, 153 F.3d at 1345;P.J.
Maffei, 732 F.2d at 916). There cannot be a differing site condition
“unless the contract indicated what that condition would be.”Comtrol
Inc. v. United States, 294 F.3d 1357, 1363
(Fed.Cir.2002) (concluding that “[b]ecause the contract made no specific
representation as to the type of soil to be encountered, it cannot be
said that [the contractor] encountered conditions materially differing
from those specifically indicated in the specification”); see
also T. Brown, 132 F.3d at 729 (requiring proof of the
government's erroneous representation as an element of a
misrepresentation claim). This issue is subject to de novo review, based
on how a reasonable contractor would interpret the contract documents as
a whole:
Determining whether a contract contained indications of a particular site condition “is a matter of contract interpretation and thus presents a question of law,” which we decide de novo. We also have stated that a proper technique of contract interpretation is for the court to place itself into the shoes of a reasonable and prudent contractor and decide how such a contractor would act in interpreting the contract documents.
H.B. Mac, 153 F.3d at
1345 (internal citation omitted) (quoting P.J. Maffei,
732 F.2d at 916).
Under the Differing Site Conditions
clause, we have on a number of occasions specifically considered whether
reports of subsurface soil conditions at particular test or boring sites
could be relied on by a reasonable contractor as an indication of the
soil conditions that would be encountered. For example, in Renda
Marine, this court held that a dredging contractor could not rely
on a set of subsurface boring reports indicating only soft, not stiff,
clays. 509 F.3d at 1376-77. These borings only reported conditions for
soil located substantially further underground than the soil that the
contractor was to dredge, and the contract documents also included
boring reports from other nearby locations indicating stiff clays at the
proper depth. Id. at 1376-78;see also Renda
Marine, Inc. v. United States, 66
Fed.Cl. 639, 657-58, 687-88 (2005). Likewise, in Comtrol, this
court held that contract documents stating “[h]ard material ... may be
encountered” did not represent that only hard material would be
encountered. 294 F.3d at 1362.
ITC has not shown that, in light of the contract documents as a whole, the clay composition levels listed in Table 2-15 of the Solvent Technology Report were an indication or representation of the clay content of the contaminated soil stockpile.
The contract
itself did not state that the contractor could rely on the
representations appearing in the reports, or in particular on the soil
composition data they provided. Instead, as discussed above, the only
mention of the Solvent Technology Report in the DO was in the first
task, which merely directed the contractor to read the Solvent
Technology Report and the Feasibility Study. The DO did not even refer
to the soil content analysis in Table 2-15 of the Solvent Technology
Report, but rather suggested only that reading the two reports would
assist the contractor in preparing a construction workplan, a quality
control plan, and a site specific health and safety plan.
Moreover, the language of the Solvent
Technology Report itself suggests that Table 2-15 was not intended as,
and would not have been reasonably interpreted as, a representative
report on the overall composition of the contaminated soil. While the
Solvent Technology Report indicated that one of its purposes was to
“[d]ocument soil characteristics,” Appellant's Supplemental App., tab 1,
at 1-9, it did not suggest that the reported soil composition test
results were intended to be representative of the overall average clay
content of the contaminated soil stockpile at the Stockton worksite.
Rather, the Solvent Technology Report indicated that these test results
were intended to identify the range of soil types that were actually
treated in the pilot study. Soil sample “[l]ocations were selected based
on visual observation of the soil types (such as fines or sand). Samples
were selected to obtain a mixture of soil types representative of the
soils to be treated during the pilot-scale treatability study.”Id.
at 4-4.
So too, the soil composition data reported in the Focused Feasibility Study reflected the presence of amounts of clay substantially exceeding ten percent. As the Board concluded, this data would have prevented a reasonable contractor from interpreting the contract documents as indicating that only a low level of clay was present in the overall soil stockpile. The Feasibility Study described a variety of soil samples and rated some as “CL.” As the Board noted, a designation of “CL” was particularly significant because this designation “meant that the majority of the weight of the soil sample was clay.”J.A. at 18. Two samples reported in Table A-8 of the Feasibility Study were designated as “CL,” i.e., they were composed of a majority of clay. Although Mr. Cash testified at trial that he did not rely on these soil composition descriptions because he did not consider the manner in which they were evaluated to be reliable, the Board explicitly rejected his testimony as based on hearsay and “not credible.” Id. FN6
Finally, section three of the Solvent Technology Report, which evaluated
TK's technology, clearly stated that “[a] soil composed primarily of
silt and clay,” such as some of the samples the Feasibility Study
reported at the Stockton site, “may not be suitable for solvent
extraction because of the excessive time required to perform the
necessary number of solvent extraction cycles to remove DDT.”
Appellant's Supplemental App., tab 1, at 3-4 .FN7This description should
have been a warning to a reasonable contractor that permeability
problems might prevent the effective use of TK's extraction technology.
Accordingly, we cannot conclude that a reasonable contractor would have read the contract as representing that the soil would contain less than ten percent clay based only on the nine soil sample compositions reported in Table 2-15 of the Solvent Technology Report.
B
Even if we
could conclude that the Solvent Technology Report represented that the
clay content of the soil stockpile would be less than ten percent, ITC
must also show that “the conditions encountered were not reasonably
foreseeable in light of all information available to [TK] when bidding
[and] that [TK] reasonably relied upon its original interpretation of
the contract.”Renda Marine, 509 F.3d at 1376;see
also T. Brown, 132 F.3d at 729 (common law inaccurate
representation claim requires showing that “contractor honestly and
reasonably relied on” government's inaccurate representation).
We review the question of whether a
contractor reasonably relied upon a representation as a question of
fact. See Renda Marine, 509 F.3d at 1378. Reliance
is unreasonable when a contractor has reason to doubt the accuracy of a
representation, such as knowledge of a flaw in the information
underlying the representation. For example, in H.B. Mac,
logs of underground borings made about three hundred yards from the site
where an underground tank was to be constructed were too far away from
the site to be reasonably relied upon because expert testimony indicated
that visible surface conditions at the worksite would have alerted a
reasonable contractor to the likelihood of highly variable subsurface
conditions. 153 F.3d at 1347.
The Board's determination here that TK could not have reasonably relied
on any representation that clay content would be below ten percent is
supported by substantial evidence. TK in this case had reason to
question the clay content figures in Table 2-15 of the Solvent
Technology Report because it was aware of a flaw in how those test
samples were obtained. TK's President and CEO, Alan Cash,
testified at trial about the manner in which the soil samples reported
in Table 2-15 of the Solvent Technology Report were collected. His
testimony demonstrates that TK had actual knowledge that these samples
were collected only from the immediate edge of the large soil stockpile
and did not include any samples from deeper within the soil stockpile.
Mr. Cash testified that at the time the soil samples described in Table 2-15 of the Solvent Technology Report were taken, the contaminated soil stockpile at the Stockton worksite was piled so that three originally separate stockpiles of contaminated soil from different locations at the facility were placed together, in adjoining piles, with a diagram indicating which portion of the stockpile originated from each of three original sites. “[T]he stockpile looked like an enormous conical pyramid with three smaller peaks.”Tr. at 1-197. Mr. Cash testified that he was present when an employee of another contractor took the soil samples reported in Table 2-15. Mr. Cash explained that the samples were collected by taking a series of random scoops of contaminated soil from the outside perimeter of each subpart of the overall stockpile (corresponding to the three original contaminated sites). He also explained that all of the samples were taken from the outer surface of the stockpile, because at the time there was no equipment at the site to enable boring or sampling the contaminated soil deeper inside.
Mr. Cash's testimony provided no basis for
an inference that these samples could be expected to be representative
of the soil deeper inside the stockpile. He relied exclusively on the
randomness of the sampling as the basis for its reliability; however,
his own testimony makes clear that the samples were not random with
respect to the whole soil stockpile, but only with respect to its
perimeter. The absence of random sampling throughout the stockpile was
particularly important because, as Mr. Cash explained, clay is often not
evenly distributed through subterranean soil at a site but instead is
often found in underground soil in a concentrated clay layer called a
lens.
Significantly,
TK itself did not use this surface sampling methodology to test the clay
content of the soil during its performance under the subcontract. Mr.
Cash testified that when TK took soil samples to evaluate the clay
content of the soil it was actually treating, during its performance
under the subcontract with ITC, it took these samples by boring at
varying depths into the soil inside its treatment bins, rather than just
at the surface, and that it did so to test whether a concentrated area
of clay was present in a particular area inside the bin.
TK could not
have reasonably relied on any representation as to the clay content of
the soil because it knew that, due to flaws in the sampling methodology
underlying Table 2-15 of the Solvent Technology Report, that table
actually revealed nothing at all about the soil toward the middle of the
stockpile.
CONCLUSION
We affirm the Board's determination
because we conclude that ITC has not established that there was any
representation in the contract documents as to the clay content of the
overall stockpile of contaminated soil and, alternatively, because ITC
has failed to establish that it would have been reasonable for TK to
rely on any such representation under the circumstances.
AFFIRMED
COSTS
No costs.
MOORE, Circuit Judge, concurs in the
result.
FN1. ITC filed a chapter 11 bankruptcy
petition on January 16, 2002. The subcontractor in this case, Terra
Kleen Response Group, Inc., was authorized by order of the bankruptcy
court to act on behalf of ITC's creditors in pursuing ITC's request for
equitable adjustment.
FN2. The total estimated cost was
substantially increased, and the time for performance extended, by a
series of contract modifications.
FN3. The referenced “task 2” called for
preparation of three plans, a “construction workplan,” a “contractor
quality control plan,” and a “site specific health and safety
plan.”Appellant's Supplemental App. at 6. The four subsequent steps
called for further planning meetings, preparation of a schedule,
treatment of the soil, preparation of a closure report, and
documentation of the process through photographs.
FN4. The Differing Site Conditions clause differentiates two distinct types of differing site condition claims: Type I claims, which involve “subsurface or latent physical conditions at the site which differ materially from those indicated in [the] contract,” and Type II claims, which involve “unknown physical conditions at the site, of an unusual nature, which differ materially from those ordinarily encountered and generally recognized as inhering in work of the character provided for in the contract.”48 C.F.R. § 52.236-2(a); see also Renda Marine, Inc. v. United States, 509 F.3d 1372, 1376 (Fed.Cir.2007) (differentiating Type I and Type II differing site conditions).
FN5. The Board held that a showing of
government culpability was also required, relying on a series of
decisions by the Court of Claims. See Foster Constr.
C.A., 435 F.2d at 881 (“Some degree of Government
culpability-either untruth or such error as is the legal equivalent-must
... be shown, and the plaintiff's burden of proof is not satisfied
merely by proof of a variation between the subsurface conditions as
stated in the contract and as encountered.”); C.W. Blakeslee
& Sons, Inc. v. United States,
89 Ct.Cl. 226 (1939); Midland Land & Improvement
Co. v. United States, 58 Ct.Cl. 671 (1923).
The government has declined to defend this holding, and we are skeptical
that such a showing is required. More recently, when this court listed
the elements of a claim for misrepresentation in a government contract
in T. Brown Constructors, Inc. v.
Pena, 132 F.3d 724, 729 (Fed.Cir.1997), we did not list any element
of government culpability. Under the general law of contracts,
essentially the same elements as those listed in the text above are
required to establish a misrepresentation claim, and no showing of
culpability is required if the representation was material. See
Restatement (Second) Contracts, ch. 7, topic 1, introductory note. As
discussed below, a similar approach, which also requires no showing of
government culpability, applies in the context of government contract
claims under the Differing Site Conditions clause. See Renda
Marine, 509 F.3d at 1377. In light of our disposition of this
case, however, we need not reach the issue of whether government
culpability must be established.
FN6. ITC urges that T. Brown
controls this case, suggesting that this case and T. Brown
involve nearly indistinguishable facts. We do not agree. In T.
Brown, this court found that a reasonable contractor could rely on
more specific information in the contract documents (there a “washed
sieve” test indicating low clay content of soil) rather than more
general information in the boring logs. 132 F.3d at 729. Critically,
nothing in any boring log at issue in T. Brown revealed
the presence of an amount of clay greater than that elsewhere
represented. Even the aggregate boring log figures (including areas of
the quarry that were not to be used) did not show a specific amount of
clay. As we stated, “[i]n sum, as the Board found, the boring logs,
‘when read together, reported no clay at some locations and strata, very
small amounts of clay in others, and unquantified amounts of clay at
other locations and strata....’ “ Id. at 728;see also
In re T. Brown Constructors, Inc.,
95-2 BCA (CCH) ¶ 27,870, at 138,979-80 (DOT BCA Aug. 18, 1995). In this
case, however, the Feasibility Study indicated a majority of clay for
some samples, and thus contradicted the data in Table 2-15 of the
Solvent Technology Report for other samples. Given this direct
contradiction, we conclude that a reasonable contractor would not have
relied exclusively on the Solvent Technology Report to conclude that the
contaminated soil would contain less than ten percent clay.
FN7. In this
regard, the Solvent Technology Report explained as follows:
The primary
difficulty encountered at NCS Stockton was the low permeability of the
soil. Removal of DDT from soils containing a large quantity of fine
particles was extremely difficult. Particle size analysis indicated silt
and clay levels in the soil ranged from 24 percent to as high as 63
percent by volume. The solvent extraction cycles took much longer than
expected due to the reduced permeability, thereby increasing treatment
time and cost. A soil composed primarily of silt and clay may not be
suitable for solvent extraction because of the excessive time required
to perform the necessary number of solvent extraction cycles to remove
DDT. The soil also tended to form clay lumps when compacted. This
resulted in the formation of soil aggregates which were difficult to
saturate with solvent, resulting in less particle contact and lower DDT
removal efficiencies. This was a particular problem with the soil at the
base of the treatment tank.
The low permeability of the soil also
significantly increased treatment time and energy costs because
providing adequate energy to the soil to vaporize the solvent was
extremely difficult.
Appellant's Supplemental App., tab 1, at
3-4-3-5 (internal citation omitted).
end |
|
Legal Do not rely on this as legal advice or a correct statement of the law. I am not an attorney. Facts differ from case to case, and the law varies from jurisdiction to jurisdiction. Always consult your attorney before doing anything that might affect your legal rights or the rights of others. |
|
CBIC is an
"A" rated property and casualty insurance company, licensed to do
business in all 50 states, and on the U. S. Treasury approved list for
Federal bonds. |
|
|
© Copyright, Contractors Bonding and Insurance
Company, 2008